Doubtnut Promotions Sticky

A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?

A

120 days

B

118 days

C

115 days

D

110 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to find out how many days C alone can complete the work given the efficiencies of A, B, and C working together in pairs. Let's break it down step by step.

Step 1: Understand the given information
- A and B can complete the work in 10 days.
- B and C can complete the work in 15 days.
- C and A can complete the work in 20 days.

Step 2: Calculate the total work
We can assume the total work to be a common multiple of the days taken by each pair. The least common multiple (LCM) of 10, 15, and 20 is 60. Thus, we can say:
- Total work = 60 units.

Step 3: Calculate the efficiencies of each pair
1. Efficiency of A and B:
A+B=60 units10 days=6 units/day

2. Efficiency of B and C:
B+C=60 units15 days=4 units/day

3. Efficiency of C and A:
C+A=60 units20 days=3 units/day

Step 4: Set up the equations
From the above calculations, we have:
1. A+B=6 (Equation 1)
2. B+C=4 (Equation 2)
3. C+A=3 (Equation 3)

Step 5: Solve the equations
To find the individual efficiencies, we can add all three equations:
(A+B)+(B+C)+(C+A)=6+4+3
This simplifies to:
2A+2B+2C=13A+B+C=132=6.5 units/day

Step 6: Find the efficiency of C
Now, we can find C's efficiency using the total efficiency:
C=(A+B+C)(A+B)=6.56=0.5 units/day

Step 7: Calculate the time taken by C alone
To find the time taken by C to complete the work alone, we use the formula:
Time=Total WorkEfficiency of C=60 units0.5 units/day=120 days

Conclusion
C alone can complete the work in 120 days.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    B and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?

    A14
    B134/11
    C144/13
    D12
  • Question 2 - Select One

    A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?

    A8
    B10
    C12
    D16
  • Question 3 - Select One

    A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A4
    B15
    C154
    D16