A can do a piece of work in 20 days. He worked for 5 days and B finished the remaining work in 42 days. B alone can do the whole work in how many days?
a)56
b)52
c)46
d)64
To solve the problem step by step, we will follow these calculations:
Step 1: Determine A's Work Rate
A can complete the entire work in 20 days. Therefore, A's work rate is:
Work rate of A=1 work20 days=120 work per day
Hint: To find the work rate, divide the total work (1 unit) by the number of days taken to complete it.
Step 2: Calculate Work Done by A in 5 Days
A worked for 5 days. The amount of work completed by A in those 5 days is:
Work done by A in 5 days=5×120=520=14 of the work
Hint: Multiply the work rate by the number of days worked to find the total work done.
Step 3: Determine Remaining Work
After A has completed 14 of the work, the remaining work is:
Remaining work=1−14=34 of the work
Hint: Subtract the completed work from the total work to find the remaining work.
Step 4: Calculate B's Work Rate
B finished the remaining 34 of the work in 42 days. Therefore, B's work rate can be calculated as:
Work rate of B=34 work42 days=34×42=3168=156 work per day
Hint: To find B's work rate, divide the amount of work done by the number of days taken.
Step 5: Calculate Total Time for B to Complete the Whole Work
Now, to find out how many days B would take to complete the entire work alone, we can use B's work rate:
Time taken by B to complete 1 work=1 work156 work per day=56 days
Hint: To find the total time taken, divide the total work (1 unit) by B's work rate.
Final Answer
B alone can do the whole work in 56 days.
---
A can complete the entire work in 20 days. Therefore, A's work rate is:
Work rate of A=1 work20 days=120 work per day
A worked for 5 days. The amount of work completed by A in those 5 days is:
Work done by A in 5 days=5×120=520=14 of the work
After A has completed 14 of the work, the remaining work is:
Remaining work=1−14=34 of the work
B finished the remaining 34 of the work in 42 days. Therefore, B's work rate can be calculated as:
Work rate of B=34 work42 days=34×42=3168=156 work per day
Now, to find out how many days B would take to complete the entire work alone, we can use B's work rate:
Time taken by B to complete 1 work=1 work156 work per day=56 days
B alone can do the whole work in 56 days.
Similar Questions
A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?
View SolutionA can do a piece of work in 80 days. A works for 10 days, then B complete the remaining work in 42 days. In how many days will (A + B) do this work together
View Solution
Knowledge Check
A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
A60B55C75D70A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
A16 daysB24 daysC28 daysD29 daysVaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
A20 daysB24 daysC18 daysD22 days
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View Solution