A can do a piece of work in 20 days. He worked for 5 days and B finished the remaining work in 42 days. B alone can do the whole work in how many days?

A

a)56

B

b)52

C

c)46

D

d)64

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow these calculations:

Step 1: Determine A's Work Rate
A can complete the entire work in 20 days. Therefore, A's work rate is:
Work rate of A=1 work20 days=120 work per day

Hint: To find the work rate, divide the total work (1 unit) by the number of days taken to complete it.

Step 2: Calculate Work Done by A in 5 Days
A worked for 5 days. The amount of work completed by A in those 5 days is:
Work done by A in 5 days=5×120=520=14 of the work

Hint: Multiply the work rate by the number of days worked to find the total work done.

Step 3: Determine Remaining Work
After A has completed 14 of the work, the remaining work is:
Remaining work=114=34 of the work

Hint: Subtract the completed work from the total work to find the remaining work.

Step 4: Calculate B's Work Rate
B finished the remaining 34 of the work in 42 days. Therefore, B's work rate can be calculated as:
Work rate of B=34 work42 days=34×42=3168=156 work per day

Hint: To find B's work rate, divide the amount of work done by the number of days taken.

Step 5: Calculate Total Time for B to Complete the Whole Work
Now, to find out how many days B would take to complete the entire work alone, we can use B's work rate:
Time taken by B to complete 1 work=1 work156 work per day=56 days

Hint: To find the total time taken, divide the total work (1 unit) by B's work rate.

Final Answer
B alone can do the whole work in 56 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?

    A60
    B55
    C75
    D70
  • A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

    A16 days
    B24 days
    C28 days
    D29 days
  • Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

    A20 days
    B24 days
    C18 days
    D22 days