Garima and her sister together can paint the walls of their house in 45 days. If Garima alone did the job, it would have taken her 81 days. If they both started painting together but Garima's sister had to leave 9 days before the completion of the work, how many days in all would it take the sisters to paint their house?
49
48
52
50
The correct Answer is:A
To solve the problem step by step, let's break down the information given and calculate the required values.
Step 1: Determine the Work Rates
1. Combined Work Rate of Garima and her Sister: They can paint the house together in 45 days.
- Work done in one day = 145 of the house.
2. Garima's Work Rate: Garima alone can paint the house in 81 days.
- Work done by Garima in one day = 181 of the house.
3. Sister's Work Rate: Let the sister's work rate be S.
- Combined work rate equation:
145=181+S
- Rearranging gives:
S=145−181
Step 2: Calculate Sister's Work Rate
To calculate S, we need a common denominator:
- The least common multiple (LCM) of 45 and 81 is 405.
Now convert the fractions:
145=9405,181=5405
Thus,
S=9405−5405=4405
So, the sister's work rate is 1101.25 of the house per day.
Step 3: Set Up the Work Equation
Let x be the total number of days taken to complete the work.
- Garima works for x days.
- The sister works for x−9 days (since she leaves 9 days before completion).
The total work done can be expressed as:
Work done by Garima+Work done by Sister=1 (whole house)
This translates to:
x81+x−9101.25=1
Step 4: Solve the Equation
To solve for x, we first convert x−9101.25 to a fraction with a common denominator:
x81+(x−9)⋅405405⋅101.25=1
This simplifies to:
x81+4(x−9)405=1
Multiplying through by 405 to eliminate the denominators:
405x81+4(x−9)=405
Calculating 40581=5:
5x+4x−36=405
Combining like terms:
9x−36=405
Adding 36 to both sides:
9x=441
Dividing by 9:
x=49
Conclusion
Thus, the total time taken by Garima and her sister to paint the house is 49 days.
1. Combined Work Rate of Garima and her Sister: They can paint the house together in 45 days.
- Work done in one day = 145 of the house.
2. Garima's Work Rate: Garima alone can paint the house in 81 days.
- Work done by Garima in one day = 181 of the house.
- Combined work rate equation:
145=181+S
- Rearranging gives:
S=145−181
To calculate S, we need a common denominator:
- The least common multiple (LCM) of 45 and 81 is 405.
145=9405,181=5405
Thus,
S=9405−5405=4405
So, the sister's work rate is 1101.25 of the house per day.
Let x be the total number of days taken to complete the work.
- Garima works for x days.
- The sister works for x−9 days (since she leaves 9 days before completion).
Work done by Garima+Work done by Sister=1 (whole house)
This translates to:
x81+x−9101.25=1
To solve for x, we first convert x−9101.25 to a fraction with a common denominator:
x81+(x−9)⋅405405⋅101.25=1
This simplifies to:
x81+4(x−9)405=1
Multiplying through by 405 to eliminate the denominators:
405x81+4(x−9)=405
Calculating 40581=5:
5x+4x−36=405
Combining like terms:
9x−36=405
Adding 36 to both sides:
9x=441
Dividing by 9:
x=49
Thus, the total time taken by Garima and her sister to paint the house is 49 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
A10B12C9D11 - Question 2 - Select One
A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?
A10B13.75C12.5D11.25 - Question 3 - Select One
A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
A6B5C7D7.2
A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionF alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
View SolutionP alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View SolutionA can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
View Solution