9 men finish one-third work in 10 days. The number of additional men required for finishing the remaining work in 2 more days will be
78
81
55
30
The correct Answer is:B
To solve the problem step by step, we can follow these calculations:
Step 1: Determine the total work done by 9 men in 10 days.
Given that 9 men finish one-third of the work in 10 days, we can denote the total work as W.
- Work done in 10 days = 13W
Step 2: Calculate the total work (W).
If 9 men complete 13W in 10 days, we can find the total work W as follows:
- Total work W=3×13W=W
Step 3: Find the work done by one man in one day.
To find out how much work one man can do in one day, we can use the following formula:
- Work done by 9 men in 10 days = 13W
- Work done by 1 man in 10 days = 13W÷9=127W
- Work done by 1 man in 1 day = 127W÷10=1270W
Step 4: Calculate the remaining work.
Since one-third of the work is completed, the remaining work is:
- Remaining work = W−13W=23W
Step 5: Determine how many men are needed to finish the remaining work in 2 days.
Let M be the number of men required to finish the remaining work in 2 days. The total work done by M men in 2 days can be expressed as:
- Work done by M men in 2 days = M×(work done by 1 man in 1 day)×2
- Work done by M men in 2 days = M×1270W×2=2M270W=M135W
Step 6: Set up the equation for the remaining work.
To finish the remaining work 23W in 2 days, we set up the equation:
M135W=23W
Step 7: Solve for M.
We can cancel W from both sides (assuming W ≠ 0):
M135=23
Now, cross-multiply to solve for M:
M=135×23=90
Step 8: Calculate the additional men required.
We already have 9 men working, so the additional men required will be:
Additional men=M−9=90−9=81
Final Answer:
The number of additional men required to finish the remaining work in 2 more days is 81.
---
Given that 9 men finish one-third of the work in 10 days, we can denote the total work as W.
If 9 men complete 13W in 10 days, we can find the total work W as follows:
To find out how much work one man can do in one day, we can use the following formula:
- Work done by 1 man in 10 days = 13W÷9=127W
- Work done by 1 man in 1 day = 127W÷10=1270W
Since one-third of the work is completed, the remaining work is:
Let M be the number of men required to finish the remaining work in 2 days. The total work done by M men in 2 days can be expressed as:
- Work done by M men in 2 days = M×1270W×2=2M270W=M135W
To finish the remaining work 23W in 2 days, we set up the equation:
We can cancel W from both sides (assuming W ≠ 0):
We already have 9 men working, so the additional men required will be:
The number of additional men required to finish the remaining work in 2 more days is 81.
Topper's Solved these Questions
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TIME AND WORKEXERCISE - Exam Booster for Cracking Exam18videos
TIME AND WORK
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TIME AND DISTANCEEXERCISE - Exam Booster for Cracking Exam25videos
TIME AND DISTANCE
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TRIGNOMETRIC RATIOS EXERCISE - Exam Booster for Cracking Exam25videos
TRIGNOMETRIC RATIOS
Similar Questions
12 men finished 14th part of whole work in 6 days. Find the number of additional men required to complete the job innext 6 days.
View Solution16 men can finish a piece of work in 49 days. 14 men started working and in 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce? 21 b. 28 c. 16 d. 14
View Solution
Knowledge Check
- Question 1 - Select One
16 men finished one-third work in 6 days. The number of additional men are required to complete the remaining job in next 6 days:
A10B8C16D32 - Question 2 - Select One
16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :
A10B8C16D32 - Question 3 - Select One
24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
Aa. 30Bb. 32Cc. 34Dd. 36
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View Solution20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
View Solution20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View SolutionP and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?
View SolutionSixteen men can finish a work in 8 days. Eight men and nine women working together can finish the same work in 10 days. In how many days will twenty women finish the same work?
View Solution