Doubtnut Promotions Sticky

9 men finish one-third work in 10 days. The number of additional men required for finishing the remaining work in 2 more days will be

A

78

B

81

C

55

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can follow these calculations:

Step 1: Determine the total work done by 9 men in 10 days.
Given that 9 men finish one-third of the work in 10 days, we can denote the total work as W.

- Work done in 10 days = 13W

Step 2: Calculate the total work (W).
If 9 men complete 13W in 10 days, we can find the total work W as follows:

- Total work W=3×13W=W

Step 3: Find the work done by one man in one day.
To find out how much work one man can do in one day, we can use the following formula:

- Work done by 9 men in 10 days = 13W
- Work done by 1 man in 10 days = 13W÷9=127W
- Work done by 1 man in 1 day = 127W÷10=1270W

Step 4: Calculate the remaining work.
Since one-third of the work is completed, the remaining work is:

- Remaining work = W13W=23W

Step 5: Determine how many men are needed to finish the remaining work in 2 days.
Let M be the number of men required to finish the remaining work in 2 days. The total work done by M men in 2 days can be expressed as:

- Work done by M men in 2 days = M×(work done by 1 man in 1 day)×2
- Work done by M men in 2 days = M×1270W×2=2M270W=M135W

Step 6: Set up the equation for the remaining work.
To finish the remaining work 23W in 2 days, we set up the equation:

M135W=23W

Step 7: Solve for M.
We can cancel W from both sides (assuming W ≠ 0):

M135=23

Now, cross-multiply to solve for M:

M=135×23=90

Step 8: Calculate the additional men required.
We already have 9 men working, so the additional men required will be:

Additional men=M9=909=81

Final Answer:
The number of additional men required to finish the remaining work in 2 more days is 81.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    16 men finished one-third work in 6 days. The number of additional men are required to complete the remaining job in next 6 days:

    A10
    B8
    C16
    D32
  • Question 2 - Select One

    16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :

    A10
    B8
    C16
    D32
  • Question 3 - Select One

    24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:

    Aa. 30
    Bb. 32
    Cc. 34
    Dd. 36