If x men can do a work in z days. Then, the number of days taken by (x + y) men to do this is
xy(x+z)
xz(x+y)
(z(x+y))/x
x(x+y)z
The correct Answer is:B
To solve the problem, we need to find out how many days it will take for (x + y) men to complete the same work that x men can do in z days.
1. Understanding the Work Done by x Men:
- If x men can complete the work in z days, then the total work can be expressed in terms of man-days.
- Total work = x men × z days = xz man-days.
2. Setting Up the Equation for (x + y) Men:
- Now, we need to find out how many days (d) it will take for (x + y) men to complete the same amount of work.
- The total work remains the same, which is xz man-days.
3. Using the Formula for Work:
- The work done by (x + y) men in d days can be expressed as:
Work=(x+y) men×d days=(x+y)⋅d man-days.
4. Setting the Two Expressions for Work Equal:
- Since both expressions represent the same total work, we can set them equal to each other:
(x+y)⋅d=xz.
5. Solving for d:
- To find d, we can rearrange the equation:
d=xzx+y.
Final Answer:
The number of days taken by (x + y) men to do the work is:
d=xzx+y.
- If x men can complete the work in z days, then the total work can be expressed in terms of man-days.
- Total work = x men × z days = xz man-days.
- Now, we need to find out how many days (d) it will take for (x + y) men to complete the same amount of work.
- The total work remains the same, which is xz man-days.
- The work done by (x + y) men in d days can be expressed as:
Work=(x+y) men×d days=(x+y)⋅d man-days.
- Since both expressions represent the same total work, we can set them equal to each other:
(x+y)⋅d=xz.
- To find d, we can rearrange the equation:
d=xzx+y.
The number of days taken by (x + y) men to do the work is:
d=xzx+y.
Topper's Solved these Questions
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TIME AND WORKEXERCISE - Exam Booster for Cracking Exam18videos
TIME AND WORK
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TIME AND DISTANCEEXERCISE - Exam Booster for Cracking Exam25videos
TIME AND DISTANCE
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TRIGNOMETRIC RATIOS EXERCISE - Exam Booster for Cracking Exam25videos
TRIGNOMETRIC RATIOS
Similar Questions
Knowledge Check
- Question 1 - Select One
If m men can do a work in r days, then the number of days taken by (m+n) men to do it is :
Am+nmnBm+nmrCmrm+nD(m+n)rmn - Question 2 - Select One
If m men can do a work in r days, then the number of days taken by (m+n) men do it is :
Am+nmnBm+nmrCmrm+nD(m+n)rmn - Question 3 - Select One
If 'b' men can do a piece of work in 'c' days, then the number of days taken by 'd' men to do 1mth of the same piece of work be
Abcd+mBbcdmCb+cd+mDb+cdm
If x men can do a piece of work In x days, then the number of days in which y men can do the same work is
View Solution2 men and 7 boys can do a piece of work in 4 days . 4 men and 4 boys can do the same work in 3 days . Then the number of days a boys a boy take to complete the same job is .
View SolutionIf 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be
View SolutionIf 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
View Solution18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day
View Solution