X can do 34 of a work in 12 days. In how many days X can finish the 1/2 work?
8 days
7 days
6 days
None of these
The correct Answer is:A
To solve the problem, we need to determine how many days X can finish half of the work if X can do 34 of the work in 12 days.
1. Understand the Work Done:
- X can complete 34 of the work in 12 days.
2. Calculate the Total Work:
- Let the total work be represented as W.
- If 34 of the work is done in 12 days, then the total work W can be calculated as:
W=12 days34=12×43=16 days
- Therefore, the total work W is equivalent to 16 days of work.
3. Determine the Work for Half:
- Half of the total work is:
12W=12×16=8 days
4. Calculate the Time Taken for Half the Work:
- Since X can complete the total work in 16 days, to find out how many days X will take to complete half the work, we can use the relationship:
Time for half work=12×Total Time=12×16=8 days
Conclusion:
X can finish half of the work in 8 days.
- X can complete 34 of the work in 12 days.
- Let the total work be represented as W.
- If 34 of the work is done in 12 days, then the total work W can be calculated as:
W=12 days34=12×43=16 days
- Therefore, the total work W is equivalent to 16 days of work.
- Half of the total work is:
12W=12×16=8 days
- Since X can complete the total work in 16 days, to find out how many days X will take to complete half the work, we can use the relationship:
Time for half work=12×Total Time=12×16=8 days
X can finish half of the work in 8 days.
Topper's Solved these Questions
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TIME AND WORKEXERCISE - Exam Booster for Cracking Exam18videos
TIME AND WORK
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TIME AND DISTANCEEXERCISE - Exam Booster for Cracking Exam25videos
TIME AND DISTANCE
- BOOK - ARIHANT PUBLICATION JHARKHANDCHAPTER - TRIGNOMETRIC RATIOS EXERCISE - Exam Booster for Cracking Exam25videos
TRIGNOMETRIC RATIOS
Similar Questions
A can do 23 of a certain work in 16 days and B can do 14 of the same work in 3 days. In how many days can both finish the work, working together?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A can do 34 of a work in 12 days. In how many days can he finish 18 of the work?
AA) 6 daysBB) 5 daysCC) 3 daysDD) 2 days - Question 2 - Select One
A can do 1/5 th of a work in 4 days and B can do 1/6th of the same work in 5 days. In how many days they can finish the work, if they work together?
A12B30C20D15 - Question 3 - Select One
A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
A56 daysB48 daysC36 daysD64 days
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionA and B can finish a work in 20 days . A alone can do 15th of the work in 12 days.In how many days can B alone do it?
View SolutionA can do 15th of a work in 4 days and B can do 16th of the same work in 5 days. In how many days they can finish the work, if they work together?
View SolutionA can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
View SolutionA and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
View Solution