Doubtnut Promotions Sticky

Ranjith can complete a task in 25 days while Anji can finish it in 20 days .They work together on the task for 5 days and then Ranjith leaves in how many days Anji finish the remaining work ?

A

15 days

B

10 days

C

11 days

D

9 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine how much work Ranjith and Anji can do together in 5 days, and then calculate how much work Anji can complete alone after Ranjith leaves.

Step 1: Calculate the work done by Ranjith and Anji in one day.

- Ranjith can complete the task in 25 days. Therefore, his work rate (efficiency) is:
Ranjith's work rate=125 of the task per day

- Anji can complete the task in 20 days. Therefore, her work rate is:
Anji's work rate=120 of the task per day

Step 2: Calculate their combined work rate.

- Together, their combined work rate is:
Combined work rate=Ranjith's work rate+Anji's work rate=125+120

To add these fractions, we need a common denominator. The least common multiple of 25 and 20 is 100.

- Converting the fractions:
125=4100and120=5100

- Now, adding them:
Combined work rate=4100+5100=9100

Thus, together they can complete 9100 of the task in one day.

Step 3: Calculate the work done in 5 days.

- In 5 days, the amount of work they complete together is:
Work done in 5 days=5×9100=45100=920

Step 4: Calculate the remaining work.

- The total work is considered as 1 (the whole task). Therefore, the remaining work after 5 days is:
Remaining work=1920=2020920=1120

Step 5: Calculate how long it takes Anji to finish the remaining work.

- Anji's work rate is 120 of the task per day. To find out how many days it takes her to complete the remaining 1120 of the task, we use the formula:
Time=Remaining workAnji's work rate=1120120=11 days

Final Answer:
Anji will finish the remaining work in 11 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?

    A5
    B18
    C25
    D20
  • Question 2 - Select One

    A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

    A17 days
    B11 days
    C10 days
    D15 days
  • Question 3 - Select One

    A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

    A7days
    B712 days
    C8 days
    D812days