Doubtnut Promotions Sticky

45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be :

A

50

B

54

C

60

D

72

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we can use the concept of work done, which is based on the formula:

Work=Number of People×Number of Days

Given that 45 people take 18 days to dig a pond, we can first calculate the total work done in terms of "person-days".

Step 1: Calculate the total work in person-days
Total Work=45 people×18 days=810 person-days

Step 2: Determine the number of people required to complete the same work in 15 days
Let x be the number of people required to complete the work in 15 days. The equation for the work done in this case will be:
Total Work=x people×15 days

Step 3: Set the two expressions for work equal to each other
810 person-days=x people×15 days

Step 4: Solve for x
To find x, we can rearrange the equation:
x=810 person-days15 days=54 people

Conclusion
Thus, the number of people required to dig the pond in 15 days is 54.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    Six people i.e. Q, W, K, U, R and L have meeting on different days of the same week starting from Monday and ends on Saturday. K has meeting just after Q but not on Thursday. Not more than two people have meeting after R. Three people have meeting between R and W. The number of people have meeting after W is same as the number of people have meeting before U. How many people have meeting before L?

    ATwo
    BOne
    CThree
    DFour
  • Question 2 - Select One

    A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A15
    B6
    C13
    D9
  • Question 3 - Select One

    A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

    A40
    B15
    C45
    D30