Doubtnut Promotions Sticky

A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

A

12

B

15

C

18

D

24

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed

    A12
    B15
    C18
    D24
  • Question 2 - Select One

    A contractor undertook to do a certain piece of work in 18 days. He employed certain number of men but 12 of them being absent from the very 1st day , the rest could finish the work in 30 days . Find the number of men originally employed .

    A40
    B15
    C45
    D30
  • Question 3 - Select One

    A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
    एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?

    A24
    B20
    C18
    D15