A, B, and C can alone do a task in 40, 120 and 36 days, respectively. A and B together work for 20 days and leave the task incomplete. C resumes it an complete it alone. How many days did C take to complete it?

A

A. 12

B

B. 20

C

C. 16

D

D. 18

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to determine how long it takes for C to complete the remaining work after A and B have worked together for 20 days. Here’s a step-by-step breakdown:

Step 1: Determine the work rates of A, B, and C
- A can complete the task in 40 days, so A's work rate is 140 of the work per day.
- B can complete the task in 120 days, so B's work rate is 1120 of the work per day.
- C can complete the task in 36 days, so C's work rate is 136 of the work per day.

Step 2: Calculate the combined work rate of A and B
To find the combined work rate of A and B, we add their individual work rates:
Work rate of A and B=140+1120
To add these fractions, we need a common denominator. The least common multiple (LCM) of 40 and 120 is 120.
140=3120and1120=1120
So,
Combined work rate=3120+1120=4120=130
This means A and B together can complete 130 of the work in one day.

Step 3: Calculate the work done by A and B in 20 days
Now, we calculate how much work A and B can complete in 20 days:
Work done in 20 days=20×130=2030=23
Thus, A and B together complete 23 of the work in 20 days.

Step 4: Determine the remaining work
The total work is considered as 1 (the whole task). Therefore, the remaining work after A and B have worked is:
Remaining work=123=13

Step 5: Calculate the time taken by C to complete the remaining work
Now we need to find out how long it will take for C to complete the remaining 13 of the work. Since C's work rate is 136 of the work per day, we can set up the equation:
Time taken by C=Remaining workWork rate of C=13136=13×36=12 days

Final Answer
C takes 12 days to complete the remaining work.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :

    A8
    B9
    C10
    D12
  • A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
    A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

    A1212days
    B1523days
    C10days
    D845days
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42