A, B, and C can alone do a task in 40, 120 and 36 days, respectively. A and B together work for 20 days and leave the task incomplete. C resumes it an complete it alone. How many days did C take to complete it?
A. 12
B. 20
C. 16
D. 18
The correct Answer is:A
To solve the problem, we need to determine how long it takes for C to complete the remaining work after A and B have worked together for 20 days. Here’s a step-by-step breakdown:
Step 1: Determine the work rates of A, B, and C
- A can complete the task in 40 days, so A's work rate is 140 of the work per day.
- B can complete the task in 120 days, so B's work rate is 1120 of the work per day.
- C can complete the task in 36 days, so C's work rate is 136 of the work per day.
Step 2: Calculate the combined work rate of A and B
To find the combined work rate of A and B, we add their individual work rates:
Work rate of A and B=140+1120
To add these fractions, we need a common denominator. The least common multiple (LCM) of 40 and 120 is 120.
140=3120and1120=1120
So,
Combined work rate=3120+1120=4120=130
This means A and B together can complete 130 of the work in one day.
Step 3: Calculate the work done by A and B in 20 days
Now, we calculate how much work A and B can complete in 20 days:
Work done in 20 days=20×130=2030=23
Thus, A and B together complete 23 of the work in 20 days.
Step 4: Determine the remaining work
The total work is considered as 1 (the whole task). Therefore, the remaining work after A and B have worked is:
Remaining work=1−23=13
Step 5: Calculate the time taken by C to complete the remaining work
Now we need to find out how long it will take for C to complete the remaining 13 of the work. Since C's work rate is 136 of the work per day, we can set up the equation:
Time taken by C=Remaining workWork rate of C=13136=13×36=12 days
Final Answer
C takes 12 days to complete the remaining work.
---
- A can complete the task in 40 days, so A's work rate is 140 of the work per day.
- B can complete the task in 120 days, so B's work rate is 1120 of the work per day.
- C can complete the task in 36 days, so C's work rate is 136 of the work per day.
To find the combined work rate of A and B, we add their individual work rates:
Work rate of A and B=140+1120
To add these fractions, we need a common denominator. The least common multiple (LCM) of 40 and 120 is 120.
140=3120and1120=1120
So,
Combined work rate=3120+1120=4120=130
This means A and B together can complete 130 of the work in one day.
Now, we calculate how much work A and B can complete in 20 days:
Work done in 20 days=20×130=2030=23
Thus, A and B together complete 23 of the work in 20 days.
The total work is considered as 1 (the whole task). Therefore, the remaining work after A and B have worked is:
Remaining work=1−23=13
Now we need to find out how long it will take for C to complete the remaining 13 of the work. Since C's work rate is 136 of the work per day, we can set up the equation:
Time taken by C=Remaining workWork rate of C=13136=13×36=12 days
C takes 12 days to complete the remaining work.
Similar Questions
If A,B and C can do a task working alone in 12, 18, and 36 days respectiel. They all work together for 2 days, then B quits. How many days A and C working together will take to complete the remainder of the task?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View Solution
Knowledge Check
Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :
A8B9C10D12A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?A1212daysB1523daysC10daysD845daysBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?
View SolutionA and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?
View SolutionA and B can complete a work in 12 days and 15 days respectively. They started the work together. If after 4 days A leaves the job, then in how many days B will complete the remaining work?
View SolutionA, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining tasks is:
A, B तथा C अकेले कार्य करते हुए किसी कार्य को क्रमशः 20, 16 तथा 30 दिनों में पूरा कर सकते हैं | यदि Aऔर B ने यह कार्य शुरू किया तथा उन्होंने 4 दिन कार्य करके छोड़ दिया , तो शेष कार्य पूरा करने में C को कितने दिन लगेंगे ?
View SolutionPersons A, B and C can complete a task together in 81 days. A and B can complete the same task together in 97.2 days. B and C can complete the same task together in 162 days. In how many days can B alone complete the task?
View Solution