Doubtnut Promotions Sticky

A and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?

A

8 days

B

6 days

C

14 days

D

12 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work rates of A and B
- A can complete the task in 40 days, so A's work rate is:
Work rate of A=1 task40 days=140 tasks per day
- B can complete the task in 16 days, so B's work rate is:
Work rate of B=1 task16 days=116 tasks per day

Step 2: Calculate the total work in terms of units
- To find a common unit for the work, we can use the least common multiple (LCM) of 40 and 16. The LCM of 40 and 16 is 80. Therefore, we can consider the total work to be 80 units.

Step 3: Calculate the work done by A in the first 12 days
- In 12 days, A will complete:
Work done by A in 12 days=12×140=1240=310 of the task
- In terms of units, this is:
Units completed by A=12×2=24 units

Step 4: Calculate the remaining work after A's initial 12 days
- The total work is 80 units, and A has completed 24 units. Therefore, the remaining work is:
Remaining work=8024=56 units

Step 5: Calculate the combined work rate of A and B
- When B joins A, their combined work rate is:
Combined work rate=140+116
- To add these fractions, we find a common denominator (which is 80):
140=280,116=580
- Therefore,
Combined work rate=280+580=780 tasks per day

Step 6: Calculate the time taken to complete the remaining work
- To find the time taken to complete the remaining 56 units of work at the combined rate of 780 tasks per day, we set up the equation:
Time=Remaining workCombined work rate=56780=56×807=44807640 days

Step 7: Final Calculation
- The exact time in days is:
Time=640÷791.43 days

Conclusion
The task lasted approximately 91.43 days after B joined.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 2 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 3 - Select One

    Pruthi and Shakil can complete a work in 20 days and 12 days respectively. Pruthi alone started the work and Shakil joined him after 4 days till the completion of the work. How long dd the work last?

    A5 days
    B10 days
    C14 days
    D22 days