A and B can together complete a tsk in 21 days. If a alone takes 42 days to complete the task, the number of days that B would take to do the task alone is :

A

42

B

36

C

27

D

32

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these calculations:

Step 1: Understand the given information
- A and B together can complete the task in 21 days.
- A alone can complete the task in 42 days.

Step 2: Calculate the total work
To find the total work, we can use the least common multiple (LCM) of the days taken by A and the days taken by A and B together.

- LCM of 21 and 42 is 42.
(Since 42 is the maximum time taken by A, it is also the LCM.)

Step 3: Calculate the efficiencies
- Efficiency of A = Total Work / Time taken by A = 42 / 42 = 1 (work units per day)
- Efficiency of A and B together = Total Work / Time taken by A and B together = 42 / 21 = 2 (work units per day)

Step 4: Find the efficiency of B
- Efficiency of B = Efficiency of A and B together - Efficiency of A
- Efficiency of B = 2 - 1 = 1 (work units per day)

Step 5: Calculate the time taken by B to complete the task alone
Using the formula:
- Work = Time × Efficiency
We can rearrange this to find the time taken by B:
- Time of B = Total Work / Efficiency of B
- Time of B = 42 / 1 = 42 days

Final Answer
B would take 42 days to complete the task alone.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B together can complete a particular task in 8 days. If
    B alone can complete the same task in 10 days, how many
    days will A take to complete the task if he works alone ?

    A28
    B36
    C40
    D32
  • Atul and Binay together complete a piece of work in 5 days. If Binay alone can complete the same work in 8 days, how many days can Atul take to complete the same work alone?
    A. 40/3 days
    B. 20/3 days
    C. 9 days
    D. 10 days

    AB
    BC
    CD
    DA
  • A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days