A and B can together complete a tsk in 21 days. If a alone takes 42 days to complete the task, the number of days that B would take to do the task alone is :
42
36
27
32
The correct Answer is:A
To solve the problem step by step, we can follow these calculations:
Step 1: Understand the given information
- A and B together can complete the task in 21 days.
- A alone can complete the task in 42 days.
Step 2: Calculate the total work
To find the total work, we can use the least common multiple (LCM) of the days taken by A and the days taken by A and B together.
- LCM of 21 and 42 is 42.
(Since 42 is the maximum time taken by A, it is also the LCM.)
Step 3: Calculate the efficiencies
- Efficiency of A = Total Work / Time taken by A = 42 / 42 = 1 (work units per day)
- Efficiency of A and B together = Total Work / Time taken by A and B together = 42 / 21 = 2 (work units per day)
Step 4: Find the efficiency of B
- Efficiency of B = Efficiency of A and B together - Efficiency of A
- Efficiency of B = 2 - 1 = 1 (work units per day)
Step 5: Calculate the time taken by B to complete the task alone
Using the formula:
- Work = Time × Efficiency
We can rearrange this to find the time taken by B:
- Time of B = Total Work / Efficiency of B
- Time of B = 42 / 1 = 42 days
Final Answer
B would take 42 days to complete the task alone.
---
- A and B together can complete the task in 21 days.
- A alone can complete the task in 42 days.
To find the total work, we can use the least common multiple (LCM) of the days taken by A and the days taken by A and B together.
(Since 42 is the maximum time taken by A, it is also the LCM.)
- Efficiency of A = Total Work / Time taken by A = 42 / 42 = 1 (work units per day)
- Efficiency of A and B together = Total Work / Time taken by A and B together = 42 / 21 = 2 (work units per day)
- Efficiency of B = Efficiency of A and B together - Efficiency of A
- Efficiency of B = 2 - 1 = 1 (work units per day)
Using the formula:
- Work = Time × Efficiency
We can rearrange this to find the time taken by B:
- Time of B = Total Work / Efficiency of B
- Time of B = 42 / 1 = 42 days
B would take 42 days to complete the task alone.
Similar Questions
Adil and Biren together can complete a task in 20 days. Biren and Chirag together can complete the same task in 50 days. Adil and Chirag together can complete the same task in 40 days. If the same task was to be done by them alone, what would be the ratio of time taken by Adil alone to taken by Biren?
(A) 11 : 9 (B) 11 : 3 (C ) 7 : 9 (D) 9 : 11
View SolutionA and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?
View Solution
Knowledge Check
A and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32Atul and Binay together complete a piece of work in 5 days. If Binay alone can complete the same work in 8 days, how many days can Atul take to complete the same work alone?
A. 40/3 days
B. 20/3 days
C. 9 days
D. 10 daysABBCCDDAA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days
A and B on working together can complete a work in 4 days. A alone takes 6 days less than B alone takes. In how many days C alone can complete the work if he is 50% more efficient than B?
View SolutionA, B and C can complete a task together in 10 days. A and B would need 12 days if only the two of them worked, while B and C would take 20 days if only the two of them worked. If B worked alone, how many days would she take to complete the task?
View SolutionA and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?
View SolutionA alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?
View SolutionPersons A, B and C can complete a task together in 81 days. A and B can complete the same task together in 97.2 days. B and C can complete the same task together in 162 days. In how many days can B alone complete the task?
View Solution