A and B can do a certain work in 12 days. B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work?
11.15 days
10.75 days
11.25 days
11.20 days
To solve the problem, we will first determine the work done by each pair of workers and then find the combined work rate of A, B, and C together.
Step 1: Determine the work rates of A, B, and C
1. Work done by A and B together:
- A and B can complete the work in 12 days.
- Therefore, their combined work rate is 112 of the work per day.
2. Work done by B and C together:
- B and C can complete the work in 15 days.
- Therefore, their combined work rate is 115 of the work per day.
3. Work done by A and C together:
- A and C can complete the work in 36 days.
- Therefore, their combined work rate is 136 of the work per day.
Step 2: Set up equations for individual work rates
Let:
- A's work rate = a
- B's work rate = b
- C's work rate = c
From the information given, we can write the following equations:
1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. a+c=136 (Equation 3)
Step 3: Solve the equations
We can solve these equations to find the individual work rates of A, B, and C.
From Equation 1:
b=112−a
Substituting b in Equation 2:
(112−a)+c=115
c=115−(112−a)
c=a−112+115
To combine the fractions, find a common denominator (which is 60):
112=560,115=460
Thus,
c=a−560+460=a−160
Substituting c in Equation 3:
a+(a−160)=136
2a−160=136
Now, convert 136 to have a common denominator of 180:
136=5180
So,
2a−3180=5180
2a=5180+3180=8180
a=4180=145
Now substitute a back to find b and c:
- From a+b=112:
145+b=112
b=112−145
Convert to a common denominator of 180:
b=15180−4180=11180
- From b+c=115:
11180+c=12180
c=12180−11180=1180
Step 4: Calculate the total work rate of A, B, and C together
Now, we can find the combined work rate of A, B, and C:
a+b+c=145+11180+1180
Convert 145 to have a denominator of 180:
145=4180
Thus,
a+b+c=4180+11180+1180=16180=445
Step 5: Find the time taken by A, B, and C together to complete the work
If their combined work rate is 445 of the work per day, the time taken to complete the work is the reciprocal of their combined work rate:
Time=1445=454=11.25 days
Final Answer
Thus, A, B, and C together will complete the work in 11.25 days.
---
- A and B can complete the work in 12 days.
- Therefore, their combined work rate is 112 of the work per day.
- B and C can complete the work in 15 days.
- Therefore, their combined work rate is 115 of the work per day.
- A and C can complete the work in 36 days.
- Therefore, their combined work rate is 136 of the work per day.
- A's work rate = a
- B's work rate = b
- C's work rate = c
2. b+c=115 (Equation 2)
3. a+c=136 (Equation 3)
b=112−a
(112−a)+c=115
c=115−(112−a)
c=a−112+115
112=560,115=460
Thus,
c=a−560+460=a−160
a+(a−160)=136
2a−160=136
136=5180
So,
2a−3180=5180
2a=5180+3180=8180
a=4180=145
- From a+b=112:
145+b=112
b=112−145
Convert to a common denominator of 180:
b=15180−4180=11180
11180+c=12180
c=12180−11180=1180
a+b+c=145+11180+1180
145=4180
Thus,
a+b+c=4180+11180+1180=16180=445
Time=1445=454=11.25 days
Thus, A, B, and C together will complete the work in 11.25 days.
Similar Questions
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View Solution
Knowledge Check
- Question 1 - Select One
B and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
A14B134/11C144/13D12 - Question 2 - Select One
24 men can do a work in 16 days while 36 women can do the same work in 24 days. In how many days will 8 men and 6 women together complete the same work ?
A36 daysB28 daysC32 daysD24 days - Question 3 - Select One
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
A8B10C12D16
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and C can do a work in 12 days while A,B and C can do the work in 4 days. In how many days can B do the work alone?
View SolutionA and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?
View SolutionA and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
View SolutionA can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
View Solution