A can finish a work in 14 days at 6 hrs a day. B can finish it in 8 days at 2 hrs a day. Find in how many days they can finish it working together 4 hrs a day.
The correct Answer is:3925
To solve the problem, we need to calculate the total work done by A and B, their individual efficiencies, and then find out how long it will take them to complete the work together when working 4 hours a day.
Step 1: Calculate the total work done by A and B.
1. Work done by A:
- A can finish the work in 14 days at 6 hours a day.
- Total hours worked by A = 14 days × 6 hours/day = 84 hours.
- Therefore, the total work (in terms of hours) = 1 work unit = 84 hours.
2. Work done by B:
- B can finish the work in 8 days at 2 hours a day.
- Total hours worked by B = 8 days × 2 hours/day = 16 hours.
- Therefore, the total work (in terms of hours) = 1 work unit = 16 hours.
Step 2: Calculate the efficiency of A and B.
1. Efficiency of A:
- Efficiency of A = Total work / Total time = 1 work unit / 84 hours = 1/84 work units per hour.
2. Efficiency of B:
- Efficiency of B = Total work / Total time = 1 work unit / 16 hours = 1/16 work units per hour.
Step 3: Calculate the combined efficiency of A and B.
- Combined efficiency = Efficiency of A + Efficiency of B
- Combined efficiency = (1/84 + 1/16)
To add these fractions, we need a common denominator:
- The least common multiple of 84 and 16 is 336.
Converting the fractions:
- (1/84) = (4/336)
- (1/16) = (21/336)
Now, adding them:
- Combined efficiency = (4/336 + 21/336) = 25/336 work units per hour.
Step 4: Calculate the total work done when working together for 4 hours a day.
- In 4 hours, the work done together = 4 hours × (25/336) work units/hour = 100/336 work units.
Step 5: Calculate the total days required to finish the work.
- Since the total work is 1 work unit, we need to find out how many days it will take to complete the work at the rate of 100/336 work units per day.
- Total days required = Total work / Work done per day = 1 / (100/336) = 336/100 = 3.36 days.
Final Answer:
They can finish the work together in approximately 3.36 days.
---
- A can finish the work in 14 days at 6 hours a day.
- Total hours worked by A = 14 days × 6 hours/day = 84 hours.
- Therefore, the total work (in terms of hours) = 1 work unit = 84 hours.
- B can finish the work in 8 days at 2 hours a day.
- Total hours worked by B = 8 days × 2 hours/day = 16 hours.
- Therefore, the total work (in terms of hours) = 1 work unit = 16 hours.
- Efficiency of A = Total work / Total time = 1 work unit / 84 hours = 1/84 work units per hour.
- Efficiency of B = Total work / Total time = 1 work unit / 16 hours = 1/16 work units per hour.
- Combined efficiency = (1/84 + 1/16)
- The least common multiple of 84 and 16 is 336.
- (1/84) = (4/336)
- (1/16) = (21/336)
- Combined efficiency = (4/336 + 21/336) = 25/336 work units per hour.
- Total days required = Total work / Work done per day = 1 / (100/336) = 336/100 = 3.36 days.
They can finish the work together in approximately 3.36 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 9 days; B and C can do it in 12 days; A and C can do it in 18 days. In how many days will A, B and C finish it working together and separately?
View SolutionA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B and C finish it, working all together?
A6 daysB514 daysC4411 daysD4 days - Question 2 - Select One
A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?
A4 daysB2 daysC3 daysD6 days - Question 3 - Select One
A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?
A4 daysB6 daysC2 daysD3 days
A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
View SolutionA can do a plece of work in 4 days and B can do it in 12 days. In how many days will they finIsh the work, both working together?
View SolutionA can do 15th of a work in 4 days and B can do 16th of the same work in 5 days. In how many days they can finish the work, if they work together?
View SolutionA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionA can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View Solution