Doubtnut Promotions Sticky

In a field 6 workers complete a task in 16 days.If this task is to be completed in 4 days,then how many workers will be required?

A

20

B

14

C

24

D

28

Text Solution
Verified by Experts

The correct Answer is:C

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Knowledge Check

  • Question 1 - Select One

    56 workers canfinish a piece of work in 14 days. If the work
    is to be completed in 8 days, then how many extra workers
    are required ?

    A36
    B48
    C44
    D42
  • Question 1 - Select One

    56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

    A7
    B8
    C14
    D16
  • Question 1 - Select One

    42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

    A7
    B6
    C14
    D16
  • Question 1 - Select One

    If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days
  • Question 1 - Select One

    A and B together can complete a particular task in 8 days. If
    B alone can complete the same task in 10 days, how many
    days will A take to complete the task if he works alone ?

    A28
    B36
    C40
    D32
  • Question 1 - Select One

    A can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?

    A60
    B54
    C48
    D45
  • Question 1 - Select One

    X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?

    A449
    B940
    C489
    D9
  • Question 1 - Select One

    If two person P and Q together can complete a task is 12 days, P alone can complete it in 48 days then in how much time Q alone can complete this task?

    A24 days
    B18 days
    C20 days
    D16 days
  • Question 1 - Select One

    A and B can together complete a tsk in 21 days. If a alone takes 42 days to complete the task, the number of days that B would take to do the task alone is :

    A42
    B36
    C27
    D32

Similar Questions