In a field 6 workers complete a task in 16 days.If this task is to be completed in 4 days,then how many workers will be required?
A
20
B
14
C
24
D
28
Text Solution
The correct Answer is:C
|
Updated on:21/07/2023
Knowledge Check
- Question 1 - Select One
56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?A36B48C44D42 - Question 1 - Select One
56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B8C14D16 - Question 1 - Select One
42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B6C14D16 - Question 1 - Select One
If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
A125 daysB122 daysC120 daysD116 days - Question 1 - Select One
A and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone ?A28B36C40D32 - Question 1 - Select One
A can complete a task alone in 9 days while B takes 13.5 days to do it by herself . Together with C it takes them 4.5 days to complete the task . If C and D together can complete the task in 18 days , then how many days will D need to complete the task by herself ?
A60B54C48D45 - Question 1 - Select One
X can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
A449B940C489D9 - Question 1 - Select One
If two person P and Q together can complete a task is 12 days, P alone can complete it in 48 days then in how much time Q alone can complete this task?
A24 daysB18 daysC20 daysD16 days - Question 1 - Select One
A and B can together complete a tsk in 21 days. If a alone takes 42 days to complete the task, the number of days that B would take to do the task alone is :
A42B36C27D32