Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days would B take to finish if he had to perform the task alone?
15
9
8
12
To solve the problem step by step, let's break it down systematically.
Step 1: Determine the total work done by A, B, and C together.
Given that A, B, and C can finish the task together in 4 days, we can calculate their combined efficiency.
- Total work = 1 task
- Time taken by A, B, and C together = 4 days
Efficiency of A, B, and C together = Total work / Time taken = 1 task / 4 days = 1/4 tasks per day.
Step 2: Determine the work done by A and C together.
After B quits, A and C finish the remaining work in 6 days.
- Time taken by A and C together = 6 days
Efficiency of A and C together = Total work / Time taken = 1 task / 6 days = 1/6 tasks per day.
Step 3: Set up equations based on efficiencies.
Let the efficiency of A be a, the efficiency of B be b, and the efficiency of C be c.
From Step 1, we have:
1. a+b+c=1/4 (Equation 1)
From Step 2, we have:
2. a+c=1/6 (Equation 2)
Step 4: Solve for B's efficiency.
Now, we can subtract Equation 2 from Equation 1 to find the efficiency of B.
From Equation 1:
a+b+c=1/4
From Equation 2:
a+c=1/6
Subtracting Equation 2 from Equation 1:
(a+b+c)−(a+c)=(1/4)−(1/6)
This simplifies to:
b=(1/4)−(1/6)
Step 5: Find a common denominator and calculate B's efficiency.
The common denominator for 4 and 6 is 12. Therefore:
1/4=3/12and1/6=2/12
Now substituting these values in:
b=(3/12)−(2/12)=1/12
Step 6: Calculate the time taken by B to finish the task alone.
Now that we have the efficiency of B, we can find out how long it would take B to complete the task alone.
Using the formula:
Time=Total WorkEfficiency of B
Substituting the values:
Time=1 task1/12 tasks per day=12 days
Final Answer:
B would take 12 days to finish the task alone.
---
Given that A, B, and C can finish the task together in 4 days, we can calculate their combined efficiency.
- Time taken by A, B, and C together = 4 days
After B quits, A and C finish the remaining work in 6 days.
Let the efficiency of A be a, the efficiency of B be b, and the efficiency of C be c.
1. a+b+c=1/4 (Equation 1)
2. a+c=1/6 (Equation 2)
Now, we can subtract Equation 2 from Equation 1 to find the efficiency of B.
a+b+c=1/4
a+c=1/6
(a+b+c)−(a+c)=(1/4)−(1/6)
This simplifies to:
b=(1/4)−(1/6)
The common denominator for 4 and 6 is 12. Therefore:
1/4=3/12and1/6=2/12
Now substituting these values in:
b=(3/12)−(2/12)=1/12
Now that we have the efficiency of B, we can find out how long it would take B to complete the task alone.
Time=Total WorkEfficiency of B
Substituting the values:
Time=1 task1/12 tasks per day=12 days
B would take 12 days to finish the task alone.
Similar Questions
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can do a task in 5 days and the total unit of work to be done is 40 units. If A alone can finish the task in 20 days, then how many days B will take to finish the task if he does alone?
A623 daysB613 daysC7 daysD2 days - Question 2 - Select One
X and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?
A45B50C60D30 - Question 3 - Select One
A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
A48 daysB88 daysC30 daysD40 days
Working together A, B and C can complete a task in 12 days. A and B can do the task in 55 days and 66 days respectively if they worked alone. In how many days can C do the task if he worked alone?
View SolutionA and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in
View SolutionA, B and C together can finish a task in 12 days. A is twice as productive as B and C alone can do the task in 36 days. In how many days can A and B do the task if C goes on leave?
View SolutionA, B and C together can finish a task in 12 days. A is twice as productive as B and C alone can do the task in 36 days. In how many days can A and B do the task if C goes on leave?
View SolutionA works twice as fast as B and B works twice as fast as C. All three working together can finish a task in 4 days with the help of D. If D alone can finish the same task in 16 days, then in how many days will A alone finish 75% of the same task ?
View Solution