Doubtnut Promotions Sticky

P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?

A

10

B

12

C

15

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Knowledge Check

  • Question 1 - Select One

    Mohit is five times more efficient as Rohit. If Mohit can complete a piece of work in 28 days less than Rohit, then in how many days can Rohit alone complete the same work?
    मोहित रोहित से पांच गुना अधिक कार्य कुशल है। अगर मोहित किसी कार्य को पूरा करने में रोहित की तुलना में 28 दिन कम का समय लेता है,तो रोहित अकेले इस कार्य को कितने दिन में पूरा करेगा ?

    A10
    B12.5
    C15
    D20
  • Question 1 - Select One

    Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then in how many days the book will be completed?

    A28
    B25
    C24
    D30
  • Question 1 - Select One

    A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?

    A15
    B17.5
    C22.5
    D27.5
  • Question 1 - Select One

    A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?

    A9
    B12
    C25
    D27
  • Question 1 - Select One

    A man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?

    A5
    B5511
    C1/11
    D11
  • Question 1 - Select One

    A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

    A17
    B19
    C19.5
    D21
  • Question 1 - Select One

    A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

    A17
    B19
    C19.5
    D21
  • Question 1 - Select One

    A is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.

    A9 days
    B12 days
    C18 days
    D24 days

Similar Questions