P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?
10
12
15
30
The correct Answer is:B
Step by step video, text & image solution for P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
The ratio of work efficiency of A & B is 2:5 . If A can complete a work in 10 days. In how many days the work can be completed by B and when they work together , in how many days the work would be completed ?
View SolutionIf man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View Solution
Knowledge Check
- Question 1 - Select One
Mohit is five times more efficient as Rohit. If Mohit can complete a piece of work in 28 days less than Rohit, then in how many days can Rohit alone complete the same work?
मोहित रोहित से पांच गुना अधिक कार्य कुशल है। अगर मोहित किसी कार्य को पूरा करने में रोहित की तुलना में 28 दिन कम का समय लेता है,तो रोहित अकेले इस कार्य को कितने दिन में पूरा करेगा ?A10B12.5C15D20 - Question 2 - Select One
Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then in how many days the book will be completed?
A28B25C24D30 - Question 3 - Select One
A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?
A15B17.5C22.5D27.5
A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?
View SolutionA man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?
View SolutionA is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
View SolutionA is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
View SolutionA is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.
View Solution