Doubtnut Promotions Sticky

P can complete a work in 72 days. Q is 33.33% more efficient
than P. In how many days both complete the work if they
work on alternate days starting with P?

A

56 days

B

60 days

C

62 days

D

none of these

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:(d)


To solve the problem step by step, let's break it down:

Step 1: Determine the work done by P and Q
P can complete the work in 72 days. Therefore, P's work rate is:
Work rate of P=172 (work per day)

Q is 33.33% more efficient than P. This means Q can do more work in a day compared to P. To find Q's efficiency, we can calculate it as follows:
Efficiency of Q=Efficiency of P×(1+33.33100)=172×43=4216=154
So, Q can complete the work in 54 days.

Step 2: Calculate the total work in terms of units
To find the total work, we can take the LCM of the days taken by P and Q:
- Days taken by P = 72
- Days taken by Q = 54

The LCM of 72 and 54 is 216. Therefore, the total work can be considered as 216 units.

Step 3: Calculate the work done by P and Q in one cycle of two days
In one day:
- Work done by P = 21672=3 units
- Work done by Q = 21654=4 units

In two days (one day of P and one day of Q):
Total work done in 2 days=3+4=7 units

Step 4: Calculate how many complete cycles can be done
To find out how many complete cycles can be done in 216 units:
Number of complete cycles=216730.857
This means they can complete 30 full cycles (60 days) and then we will have some work left.

Step 5: Calculate the work done in 60 days
In 60 days, the total work done is:
Total work done in 60 days=30×7=210 units

Step 6: Calculate the remaining work
The remaining work after 60 days is:
Remaining work=216210=6 units

Step 7: Determine who will do the remaining work
On the 61st day, P will work. P can do 3 units of work in one day. Since the remaining work is 6 units, P will do 3 units on the 61st day, leaving 3 units.

On the 62nd day, Q will work. Q can do 4 units of work in one day. Q will complete the remaining 3 units on the 62nd day.

Step 8: Calculate the total days taken
Total days taken:
- 60 days for the complete cycles
- 1 day for P (61st day)
- 1 day for Q (62nd day)

Thus, the total days taken is:
Total days=60+1+1=62 days

Final Answer
Both P and Q can complete the work in 62 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P can do a work in 9 days and Q is 50% more efficient than P. In how many days can Q do it alone ?

    A1312
    B412
    C6
    D3
  • Question 2 - Select One

    P and Q can individually complete a piece of work in 15 and 25 days respectively.In how many days can P and Q complete the work if they work in alternative days ?
    Starting with P
    Starting with Q?

    A18, 19
    B18,1915
    C1835,19
    D1825,19
  • Question 3 - Select One

    A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is

    A6
    B712
    C8
    D812