Doubtnut Promotions Sticky

P can complete a work in 72 days. Q is 33.33% more efficient
than P. In how many days both complete the work if they
work on alternate days starting with P?

A

56 days

B

60 days

C

62 days

D

none of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:(d)


Q will complete the work alone in -
34×72=54 days
ocr_image
Let total units of work = 216
No. Of units done by P in 1 days = 3
No. of units done by Q in 1 day = 4
Total work done in 2 days = 7 units
Work done in 60 days =7×30=210 units
Remaining work =6unit
work done by P in 1day=3 unit
Remaining work done by Q=34 day.
Total days taken =(60+1+34) days
=6134 days

|
Updated on:21/07/2023

Related Playlists


Similar Questions