A can do a piece of work in 48 days and B can do the same work in 64 days, while C take as half time as A and B take together. If they start working alternatively, starting by C, followed by B and then A respectively, then find in how many days work will be completed?
A)2637days
B)2857days
C)26114days
D)27314days
The correct Answer is:D
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work rates of A, B, and C
- A can complete the work in 48 days. Therefore, A's work rate is:
Work rate of A=148 work/day
- B can complete the work in 64 days. Therefore, B's work rate is:
Work rate of B=164 work/day
Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B is:
Combined work rate of A and B=148+164
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 48 and 64 is 192.
148=4192,164=3192
- Therefore,
Combined work rate of A and B=4+3192=7192 work/day
Step 3: Determine C's work rate
- C takes half the time of A and B working together. The time taken by A and B together to complete the work is:
Time taken by A and B together=1927 days
- Therefore, C's time to complete the work is:
Time taken by C=12×1927=967 days
- C's work rate is:
Work rate of C=1967=796 work/day
Step 4: Calculate the total work done in one complete cycle of C, B, and A
- In one cycle (3 days), the work done is:
- Day 1 (C): C does 796
- Day 2 (B): B does 164
- Day 3 (A): A does 148
- Total work done in one cycle:
Total work in 3 days=796+164+148
Step 5: Find a common denominator and calculate the total work done in one cycle
- The common denominator for 96, 64, and 48 is 192.
796=14192,164=3192,148=4192
- Therefore,
Total work in 3 days=14+3+4192=21192 work
Step 6: Calculate how many complete cycles are needed to finish the work
- The total work is 1 (or 192/192). The number of complete cycles needed:
Number of cycles=19221≈9.14 cycles
- This means 9 complete cycles can be done, which takes:
9×3=27 days
Step 7: Calculate the remaining work after 9 cycles
- Work done in 9 cycles:
9×21192=189192
- Remaining work:
1−189192=3192=164
Step 8: Determine how long it will take to finish the remaining work
- C starts the next cycle and can complete 796 work in one day. To finish 164:
- Time taken by C to finish 164:
Time=164796=96448=314 days
Final Calculation
- Total time taken to complete the work:
27+314=27314 days
Conclusion
The total time taken to complete the work is 27 whole 3/14 days.
- A can complete the work in 48 days. Therefore, A's work rate is:
Work rate of A=148 work/day
- B can complete the work in 64 days. Therefore, B's work rate is:
Work rate of B=164 work/day
- The combined work rate of A and B is:
Combined work rate of A and B=148+164
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 48 and 64 is 192.
148=4192,164=3192
- Therefore,
Combined work rate of A and B=4+3192=7192 work/day
- C takes half the time of A and B working together. The time taken by A and B together to complete the work is:
Time taken by A and B together=1927 days
- Therefore, C's time to complete the work is:
Time taken by C=12×1927=967 days
- C's work rate is:
Work rate of C=1967=796 work/day
- In one cycle (3 days), the work done is:
- Day 1 (C): C does 796
- Day 2 (B): B does 164
- Day 3 (A): A does 148
Total work in 3 days=796+164+148
- The common denominator for 96, 64, and 48 is 192.
796=14192,164=3192,148=4192
- Therefore,
Total work in 3 days=14+3+4192=21192 work
- The total work is 1 (or 192/192). The number of complete cycles needed:
Number of cycles=19221≈9.14 cycles
- This means 9 complete cycles can be done, which takes:
9×3=27 days
- Work done in 9 cycles:
9×21192=189192
- Remaining work:
1−189192=3192=164
- C starts the next cycle and can complete 796 work in one day. To finish 164:
- Time taken by C to finish 164:
Time=164796=96448=314 days
- Total time taken to complete the work:
27+314=27314 days
The total time taken to complete the work is 27 whole 3/14 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
A15B16C10D12 - Question 2 - Select One
A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?
A5B6C823D2025 - Question 3 - Select One
A can do a work in 12 days while B can do same work in 18 days. How long(in days) will it take if they do the work together?
A किसी कार्य को 12 दिनों में कर सकता है जबकि B इसी कार्य को 18 दिनों में कर सकता है | यदि वे साथ कार्य करें तो इसे पूरा होने में कितने दिन लगेंगे ?A553B715C615D623
(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionIf A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?
View SolutionA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
View SolutionA can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
View Solution