A can do a piece of work in 48 days and B can do the same work in 64 days, while C take as half time as A and B take together. If they start working alternatively, starting by C, followed by B and then A respectively, then find in how many days work will be completed?

A

A)2637days

B

B)2857days

C

C)26114days

D

D)27314days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 48 days. Therefore, A's work rate is:
Work rate of A=148 work/day
- B can complete the work in 64 days. Therefore, B's work rate is:
Work rate of B=164 work/day

Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B is:
Combined work rate of A and B=148+164
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 48 and 64 is 192.
148=4192,164=3192
- Therefore,
Combined work rate of A and B=4+3192=7192 work/day

Step 3: Determine C's work rate
- C takes half the time of A and B working together. The time taken by A and B together to complete the work is:
Time taken by A and B together=1927 days
- Therefore, C's time to complete the work is:
Time taken by C=12×1927=967 days
- C's work rate is:
Work rate of C=1967=796 work/day

Step 4: Calculate the total work done in one complete cycle of C, B, and A
- In one cycle (3 days), the work done is:
- Day 1 (C): C does 796
- Day 2 (B): B does 164
- Day 3 (A): A does 148

- Total work done in one cycle:
Total work in 3 days=796+164+148

Step 5: Find a common denominator and calculate the total work done in one cycle
- The common denominator for 96, 64, and 48 is 192.
796=14192,164=3192,148=4192
- Therefore,
Total work in 3 days=14+3+4192=21192 work

Step 6: Calculate how many complete cycles are needed to finish the work
- The total work is 1 (or 192/192). The number of complete cycles needed:
Number of cycles=192219.14 cycles
- This means 9 complete cycles can be done, which takes:
9×3=27 days

Step 7: Calculate the remaining work after 9 cycles
- Work done in 9 cycles:
9×21192=189192
- Remaining work:
1189192=3192=164

Step 8: Determine how long it will take to finish the remaining work
- C starts the next cycle and can complete 796 work in one day. To finish 164:
- Time taken by C to finish 164:
Time=164796=96448=314 days

Final Calculation
- Total time taken to complete the work:
27+314=27314 days

Conclusion
The total time taken to complete the work is 27 whole 3/14 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?

    A15
    B16
    C10
    D12
  • Question 2 - Select One

    A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?

    A5
    B6
    C823
    D2025
  • Question 3 - Select One

    A can do a work in 12 days while B can do same work in 18 days. How long(in days) will it take if they do the work together?
    A किसी कार्य को 12 दिनों में कर सकता है जबकि B इसी कार्य को 18 दिनों में कर सकता है | यदि वे साथ कार्य करें तो इसे पूरा होने में कितने दिन लगेंगे ?

    A553
    B715
    C615
    D623