X is 40% more efficient than Y and Z takes 33 1 3 % less time than X to complete a work. If all three together can complete a work in 6 2 9 days, then find X & Z can complete the two times of work in how many days?

A

A)8 days

B

B)16 days

C

C)18 days

D

D)32 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow the reasoning and calculations as outlined in the video transcript.

Step 1: Determine the Efficiency Ratio of X and Y
X is 40% more efficient than Y. If we assume Y's efficiency is 5 units, then:
- X's efficiency = Y's efficiency + 40% of Y's efficiency
- X's efficiency = 5 + (40/100) * 5 = 5 + 2 = 7 units

Thus, the efficiency ratio of X to Y is:
- X : Y = 7 : 5

Hint: To find the efficiency of X when given a percentage increase, convert the percentage to a fraction and apply it to the base efficiency.

Step 2: Determine the Efficiency Ratio of Z
Z takes 33⅓% less time than X. This means Z is more efficient than X.
- 33⅓% can be expressed as 1/3.
If X takes 3 units of time, then Z takes:
- Z's time = 3 - (1/3 * 3) = 3 - 1 = 2 units

Since efficiency is inversely proportional to time:
- Efficiency of Z = 1 / (time taken by Z) = 3/2 units

Thus, the efficiency ratio of X to Z is:
- X : Z = 2 : 3

Hint: When time decreases by a certain percentage, the efficiency increases by the same proportion. Use the inverse relationship between time and efficiency.

Step 3: Combine the Efficiency Ratios
Now we have:
- X : Y = 7 : 5
- X : Z = 2 : 3

To combine these ratios, we need a common term for X. We can express the ratios as:
- X : Y : Z = 14 : 10 : 21

Hint: To combine ratios, find a common term (in this case, X) and adjust the other parts of the ratio accordingly.

Step 4: Calculate Total Work Done
We know that all three together can complete the work in 629 days. First, convert this to an improper fraction:
- 629=569 days.

Total efficiency of X, Y, and Z:
- Total efficiency = 14 + 10 + 21 = 45 units.

Total work done can be calculated as:
- Total work = Total efficiency × Time = 45 × 569
- Total work = 25209=280 units.

Hint: To find total work, multiply the total efficiency by the time taken to complete the work.

Step 5: Calculate Time Taken by X and Z to Complete Double the Work
If X and Z work together to complete double the work:
- Double work = 280 × 2 = 560 units.

Efficiency of X and Z together:
- Efficiency of X and Z = 14 + 21 = 35 units.

Time taken by X and Z to complete double the work:
- Time = Total work / Combined efficiency = 56035
- Time = 16 days.

Hint: When calculating time for a given amount of work, divide the total work by the combined efficiency of the workers.

Final Answer
X and Z can complete double the work in 16 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?

    A10
    B12
    C14
    D15
  • Question 2 - Select One

    A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?

    A10
    B12
    C14
    D16
  • Question 3 - Select One

    Raman is 25% more efficient than Aman. If Aman can complete a piece of work in 25 days, then Raman can complete the same work in how many days?

    A12
    B15
    C16
    D20