X is 40% more efficient than Y and Z takes less time than X to complete a work. If all three together can complete a work in days, then find X & Z can complete the two times of work in how many days?
A)8 days
B)16 days
C)18 days
D)32 days
The correct Answer is:B
To solve the problem step by step, we will follow the reasoning and calculations as outlined in the video transcript.
Step 1: Determine the Efficiency Ratio of X and Y
X is 40% more efficient than Y. If we assume Y's efficiency is 5 units, then:
- X's efficiency = Y's efficiency + 40% of Y's efficiency
- X's efficiency = 5 + (40/100) * 5 = 5 + 2 = 7 units
Thus, the efficiency ratio of X to Y is:
- X : Y = 7 : 5
Hint: To find the efficiency of X when given a percentage increase, convert the percentage to a fraction and apply it to the base efficiency.
Step 2: Determine the Efficiency Ratio of Z
Z takes 33⅓% less time than X. This means Z is more efficient than X.
- 33⅓% can be expressed as 1/3.
If X takes 3 units of time, then Z takes:
- Z's time = 3 - (1/3 * 3) = 3 - 1 = 2 units
Since efficiency is inversely proportional to time:
- Efficiency of Z = 1 / (time taken by Z) = 3/2 units
Thus, the efficiency ratio of X to Z is:
- X : Z = 2 : 3
Hint: When time decreases by a certain percentage, the efficiency increases by the same proportion. Use the inverse relationship between time and efficiency.
Step 3: Combine the Efficiency Ratios
Now we have:
- X : Y = 7 : 5
- X : Z = 2 : 3
To combine these ratios, we need a common term for X. We can express the ratios as:
- X : Y : Z = 14 : 10 : 21
Hint: To combine ratios, find a common term (in this case, X) and adjust the other parts of the ratio accordingly.
Step 4: Calculate Total Work Done
We know that all three together can complete the work in 629 days. First, convert this to an improper fraction:
- 629=569 days.
Total efficiency of X, Y, and Z:
- Total efficiency = 14 + 10 + 21 = 45 units.
Total work done can be calculated as:
- Total work = Total efficiency × Time = 45 × 569
- Total work = 25209=280 units.
Hint: To find total work, multiply the total efficiency by the time taken to complete the work.
Step 5: Calculate Time Taken by X and Z to Complete Double the Work
If X and Z work together to complete double the work:
- Double work = 280 × 2 = 560 units.
Efficiency of X and Z together:
- Efficiency of X and Z = 14 + 21 = 35 units.
Time taken by X and Z to complete double the work:
- Time = Total work / Combined efficiency = 56035
- Time = 16 days.
Hint: When calculating time for a given amount of work, divide the total work by the combined efficiency of the workers.
Final Answer
X and Z can complete double the work in 16 days.
X is 40% more efficient than Y. If we assume Y's efficiency is 5 units, then:
- X's efficiency = Y's efficiency + 40% of Y's efficiency
- X's efficiency = 5 + (40/100) * 5 = 5 + 2 = 7 units
- X : Y = 7 : 5
Z takes 33⅓% less time than X. This means Z is more efficient than X.
- 33⅓% can be expressed as 1/3.
If X takes 3 units of time, then Z takes:
- Z's time = 3 - (1/3 * 3) = 3 - 1 = 2 units
- Efficiency of Z = 1 / (time taken by Z) = 3/2 units
- X : Z = 2 : 3
Now we have:
- X : Y = 7 : 5
- X : Z = 2 : 3
- X : Y : Z = 14 : 10 : 21
We know that all three together can complete the work in 629 days. First, convert this to an improper fraction:
- 629=569 days.
- Total efficiency = 14 + 10 + 21 = 45 units.
- Total work = Total efficiency × Time = 45 × 569
- Total work = 25209=280 units.
If X and Z work together to complete double the work:
- Double work = 280 × 2 = 560 units.
- Efficiency of X and Z = 14 + 21 = 35 units.
- Time = Total work / Combined efficiency = 56035
- Time = 16 days.
X and Z can complete double the work in 16 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?
View SolutionA takes 412 days more than (A + B) together to complete a work. B takes 8 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View Solution
Knowledge Check
- Question 1 - Select One
A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
A10B12C14D15 - Question 2 - Select One
A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
A10B12C14D16 - Question 3 - Select One
Raman is 25% more efficient than Aman. If Aman can complete a piece of work in 25 days, then Raman can complete the same work in how many days?
A12B15C16D20
Vijay is 10% more efficient than Vikas. If Vikas can complete a piece of work in 33 days. Then Vijay can complete the same work in how many days ?
View SolutionX, Y and Z together can complete a work in 20 days. Y and Z can complete the same work in 30 days. In how many days X alone can complete the same work?
View SolutionA work three times as fast as B.B takes 56 days more than A to complete a work. Working together in how days can they complete the work?
View SolutionA is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
View SolutionA is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
View Solution