A is thrice as good a workman as B and therefore is able to finish a job in 80 days less than B. If A and B complete 58th of the job and then A is replaced by C, the remaining job is done by B and C in 15 days. If A and B complete 512th of the job and then B is replaced by D the remaining job is done by A and D in 10 days.
How long will it take to complete the job, if A,B,C and D working together?
12 days
10 days
15 days
18 days
The correct Answer is:A
To solve the problem step by step, we will first determine the efficiencies of A, B, C, and D, and then calculate how long it will take for all of them to complete the job together.
Step 1: Determine the efficiencies of A and B
Given that A is thrice as good a workman as B, we can denote:
- Efficiency of B = 1 unit of work per day
- Efficiency of A = 3 units of work per day
Let the time taken by B to complete the job be x days. Since A finishes the job in 80 days less than B, we have:
Time taken by A=x−80
Using the formula for work:
Total Work=Efficiency×Time
For A:
3(x−80)=Total Work
For B:
1×x=Total Work
Setting these equal gives:
3(x−80)=x
Expanding and simplifying:
3x−240=x
2x=240
x=120
So, B takes 120 days to complete the job, and A takes:
120−80=40 days
Step 2: Calculate the total work
Using B's time:
Total Work=1×120=120 units
Step 3: Work done by A and B together
A and B together complete 58 of the job:
Work done=58×120=75 units
Step 4: Remaining work
Remaining work after A and B:
120−75=45 units
Step 5: Work done by B and C
B and C complete the remaining 45 units in 15 days. Therefore, their combined efficiency is:
Efficiency of B and C=4515=3 units per day
Since B's efficiency is 1 unit per day, we can find C's efficiency:
1+C=3
C=2 units per day
Step 6: Work done by A and B together again
Next, A and B complete 512 of the job:
Work done=512×120=50 units
Step 7: Remaining work
Remaining work after A and B:
120−50=70 units
Step 8: Work done by A and D
A and D complete the remaining 70 units in 10 days. Therefore, their combined efficiency is:
Efficiency of A and D=7010=7 units per day
Since A's efficiency is 3 units per day, we can find D's efficiency:
3+D=7
D=4 units per day
Step 9: Total efficiency of A, B, C, and D together
Now, we can find the total efficiency when A, B, C, and D work together:
Total Efficiency=A+B+C+D=3+1+2+4=10 units per day
Step 10: Time taken to complete the job together
Finally, to find the time taken to complete the entire job when A, B, C, and D work together:
Time=Total WorkTotal Efficiency=12010=12 days
Final Answer
Thus, it will take 12 days to complete the job if A, B, C, and D work together.
---
Given that A is thrice as good a workman as B, we can denote:
- Efficiency of B = 1 unit of work per day
- Efficiency of A = 3 units of work per day
Time taken by A=x−80
Total Work=Efficiency×Time
For A:
3(x−80)=Total Work
For B:
1×x=Total Work
3(x−80)=x
Expanding and simplifying:
3x−240=x
2x=240
x=120
120−80=40 days
Using B's time:
Total Work=1×120=120 units
A and B together complete 58 of the job:
Work done=58×120=75 units
Remaining work after A and B:
120−75=45 units
B and C complete the remaining 45 units in 15 days. Therefore, their combined efficiency is:
Efficiency of B and C=4515=3 units per day
1+C=3
C=2 units per day
Next, A and B complete 512 of the job:
Work done=512×120=50 units
Remaining work after A and B:
120−50=70 units
A and D complete the remaining 70 units in 10 days. Therefore, their combined efficiency is:
Efficiency of A and D=7010=7 units per day
3+D=7
D=4 units per day
Now, we can find the total efficiency when A, B, C, and D work together:
Total Efficiency=A+B+C+D=3+1+2+4=10 units per day
Finally, to find the time taken to complete the entire job when A, B, C, and D work together:
Time=Total WorkTotal Efficiency=12010=12 days
Thus, it will take 12 days to complete the job if A, B, C, and D work together.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in
A14 daysB13 daysC20 daysD15 days - Question 2 - Select One
A is thrice as good a workman B and therefore is able to finish a job in 40 days less titan B. Working together, they can do it in
A14 daysB13 daysC20 daysD15 days - Question 3 - Select One
A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?
A1014B1134C1114D1113
P is thrice as good a workman as Q and therefore able to finish a Job in 48 days less than . Working together, they can do it in :
View SolutionHow many men need to be emloyed to complete a job in 5 days, if 15 men can complete 13 of the job in 7 days?
View SolutionA and B can do a job in 12 days, B and C in 15 days and C and A in 20 days. How long would A take to do that work?
View SolutionA completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
View SolutionB is twice as fast as A and C is three times as fast as A. If B alone can complete a job in 12 days, how long will A, B and C take to complete the same job together?
View Solution