Doubtnut Promotions Sticky

A is thrice as good a workman as B and therefore is able to finish a job in 80 days less than B. If A and B complete 58th of the job and then A is replaced by C, the remaining job is done by B and C in 15 days. If A and B complete 512th of the job and then B is replaced by D the remaining job is done by A and D in 10 days.
How long will it take to complete the job, if A,B,C and D working together?

A

12 days

B

10 days

C

15 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the efficiencies of A, B, C, and D, and then calculate how long it will take for all of them to complete the job together.

Step 1: Determine the efficiencies of A and B
Given that A is thrice as good a workman as B, we can denote:
- Efficiency of B = 1 unit of work per day
- Efficiency of A = 3 units of work per day

Let the time taken by B to complete the job be x days. Since A finishes the job in 80 days less than B, we have:
Time taken by A=x80

Using the formula for work:
Total Work=Efficiency×Time
For A:
3(x80)=Total Work
For B:
1×x=Total Work

Setting these equal gives:
3(x80)=x
Expanding and simplifying:
3x240=x
2x=240
x=120

So, B takes 120 days to complete the job, and A takes:
12080=40 days

Step 2: Calculate the total work
Using B's time:
Total Work=1×120=120 units

Step 3: Work done by A and B together
A and B together complete 58 of the job:
Work done=58×120=75 units

Step 4: Remaining work
Remaining work after A and B:
12075=45 units

Step 5: Work done by B and C
B and C complete the remaining 45 units in 15 days. Therefore, their combined efficiency is:
Efficiency of B and C=4515=3 units per day

Since B's efficiency is 1 unit per day, we can find C's efficiency:
1+C=3
C=2 units per day

Step 6: Work done by A and B together again
Next, A and B complete 512 of the job:
Work done=512×120=50 units

Step 7: Remaining work
Remaining work after A and B:
12050=70 units

Step 8: Work done by A and D
A and D complete the remaining 70 units in 10 days. Therefore, their combined efficiency is:
Efficiency of A and D=7010=7 units per day

Since A's efficiency is 3 units per day, we can find D's efficiency:
3+D=7
D=4 units per day

Step 9: Total efficiency of A, B, C, and D together
Now, we can find the total efficiency when A, B, C, and D work together:
Total Efficiency=A+B+C+D=3+1+2+4=10 units per day

Step 10: Time taken to complete the job together
Finally, to find the time taken to complete the entire job when A, B, C, and D work together:
Time=Total WorkTotal Efficiency=12010=12 days

Final Answer
Thus, it will take 12 days to complete the job if A, B, C, and D work together.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in

    A14 days
    B13 days
    C20 days
    D15 days
  • Question 2 - Select One

    A is thrice as good a workman B and therefore is able to finish a job in 40 days less titan B. Working together, they can do it in

    A14 days
    B13 days
    C20 days
    D15 days
  • Question 3 - Select One

    A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?

    A1014
    B1134
    C1114
    D1113