Doubtnut Promotions Sticky

Efficiency of A is two times more than efficiency of B. Both A & B start working alternatively, starting with A and they complete the work in total 7423 days. C can alone complete the same work in 100 days.
If efficiency of D is 3313% more than that of C, then find time taken by A & D together to complete the work?

A

30 days

B

20 days

C

24 days

D

36 days

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for Efficiency of A is two times more than efficiency of B. Both A & B start working alternatively, starting with A and they complete the work in total 74(2)/(3) days. C can alone complete the same work in 100 days. If efficiency of D is 33(1)/(3)% more than that of C, then find time taken by A & D together to complete the work? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Efficiency of Q is two times more than efficiency of P. Both
    started working alternatively, starting with Q and completed
    the work in total 35 days. If R alone complete the same work in
    48 days then find in how many days P and R together will
    complete the work?

    A24 days
    B28 days
    C36 days
    D27 days
  • Question 2 - Select One

    To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in 1712 days. A alone will complete 60% of the same work in:

    A21 days
    B16 days
    C15 days
    D18 days
  • Question 3 - Select One

    A and B can together complete a work in 16 days. B and C can together complete the same work in 24 days and A, B and C together can complete the work in 12 days. Find time taken by A and C to complete the work together.
    (a)12 days
    (b)14 days
    (c)16 days
    (d)18 days

    A12 days
    B14 days
    C16 days
    D18 days