Doubtnut Promotions Sticky

P and Q together can complete a work in 24 days, while Q and R working together can complete the same job in 32 days. P and Q started the work and did it for 8 days, after that P left the work and R joined Q and after 12 more days, Q also left the work. Then, the remaining work was completed by R in 28 days. Find in how many days R will complete the work alone?

A

96 days

B

72 days

C

108 days

D

90 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will break down the information provided and calculate the required values systematically.

Step 1: Calculate Total Work
P and Q together can complete the work in 24 days. Therefore, their combined efficiency is:
Efficiency of P + Q=124 work/day
Similarly, Q and R can complete the work in 32 days, so their combined efficiency is:
Efficiency of Q + R=132 work/day

To find the total work, we can use the least common multiple (LCM) of the two time periods:
Total Work=LCM(24,32)=96 units of work

Step 2: Calculate Individual Efficiencies
From the efficiencies calculated:
- Let the efficiency of P be p, Q be q, and R be r.
- We have:
p+q=9624=4 (units of work/day)
q+r=9632=3 (units of work/day)

Step 3: Set Up Equations
Now, we can set up the equations:
1. p+q=4
2. q+r=3

From the first equation, we can express p in terms of q:
p=4q

Substituting p into the second equation:
(4q)+r=3
This simplifies to:
r=34+q=q1

Step 4: Calculate Work Done by P and Q
P and Q work together for 8 days:
Work done by P + Q in 8 days=8×4=32 units

Step 5: Calculate Remaining Work
The total work is 96 units, so the remaining work after P and Q have worked for 8 days is:
Remaining Work=9632=64 units

Step 6: Calculate Work Done by Q and R
Next, Q and R work together for 12 days:
Work done by Q + R in 12 days=12×3=36 units

Step 7: Calculate Remaining Work After Q and R
After Q and R have worked for 12 days, the remaining work is:
Remaining Work=6436=28 units

Step 8: Calculate Work Done by R
R completes the remaining 28 units of work in 28 days:
Efficiency of R=28 units28 days=1 unit of work/day

Step 9: Calculate Time Taken by R Alone
To find out how many days R will take to complete the entire work alone:
Time taken by R=Total WorkEfficiency of R=961=96 days

Final Answer
R will complete the work alone in 96 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

    A40
    B72
    C84
    D90
  • Question 2 - Select One

    P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

    A1800
    B900
    C1200
    D1500
  • Question 3 - Select One

    P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

    A48 days
    B42 days
    C45 days
    D51 days