Doubtnut Promotions Sticky

X' men can complete a work in 4 days. '(X-2)' women can complete the same work in 8 days, while ratio of efficiency of man to woman is 3 : 2. If x 2 men & '(X - 2)' women started the work & worked for only 2 days then, how many women should replace to men to complete the remaining work in three days?

A

2 women

B

8 women

C

6 women

D

4 women

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will break down the information given and calculate accordingly.

Step 1: Calculate Total Work Done by Men and Women
Given:
- X men can complete the work in 4 days.
- (X2) women can complete the same work in 8 days.
- The efficiency ratio of men to women is 3:2.

Let the efficiency of one man be M=3k and the efficiency of one woman be W=2k.

Total work done by men:
Total Work=Number of Men×Efficiency of Men×Time
=X×3k×4=12Xk

Total work done by women:
Total Work=Number of Women×Efficiency of Women×Time
=(X2)×2k×8=16(X2)k

Since both expressions represent the same total work, we can set them equal:
12Xk=16(X2)k

Step 2: Simplify the Equation
Dividing both sides by k (assuming k0):
12X=16(X2)
Expanding the right side:
12X=16X32
Rearranging gives:
32=16X12X
32=4X
X=8

Step 3: Calculate the Number of Men and Women
Now substituting X back:
- Number of Men = X=8
- Number of Women = X2=6

Step 4: Work Done in 2 Days
Now, X2=82=4 men and (X2)=6 women start the work.

Daily work done:
Work by Men in 1 day=4×3=12
Work by Women in 1 day=6×2=12
Total Work in 1 day=12+12=24

Work done in 2 days:
Total Work in 2 days=24×2=48

Step 5: Calculate Remaining Work
Total Work:
Total Work=12Xk=12×8k=96k

Remaining Work:
Remaining Work=96k48=48k

Step 6: Work Required in 3 Days
To complete the remaining work in 3 days:
Work required per day=48k3=16k

Step 7: Determine How Many Women are Needed
Let Y be the number of women replacing men. The efficiency of Y women is:
Work done by Y women in 1 day=Y×2k

Setting the total work done in a day to 16k:
Y×2k=16k
Dividing both sides by 2k:
Y=8

Step 8: Calculate the Number of Women to Replace
Initially, there were 6 women. To find how many women need to be added:
Women to replace=Y6=86=2

Final Answer
The number of women that should replace men to complete the remaining work in three days is 2.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days

    A6
    B5
    C4
    D2
  • Question 2 - Select One

    If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days

    A6
    B5
    C4
    D2
  • Question 3 - Select One

    If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days

    A6
    B5
    C4
    D2