X' men can complete a work in 4 days. '(X-2)' women can complete the same work in 8 days, while ratio of efficiency of man to woman is 3 : 2. If men & '(X - 2)' women started the work & worked for only 2 days then, how many women should replace to men to complete the remaining work in three days?
2 women
8 women
6 women
4 women
The correct Answer is:A
To solve the problem step by step, we will break down the information given and calculate accordingly.
Step 1: Calculate Total Work Done by Men and Women
Given:
- X men can complete the work in 4 days.
- (X−2) women can complete the same work in 8 days.
- The efficiency ratio of men to women is 3:2.
Let the efficiency of one man be M=3k and the efficiency of one woman be W=2k.
Total work done by men:
Total Work=Number of Men×Efficiency of Men×Time
=X×3k×4=12Xk
Total work done by women:
Total Work=Number of Women×Efficiency of Women×Time
=(X−2)×2k×8=16(X−2)k
Since both expressions represent the same total work, we can set them equal:
12Xk=16(X−2)k
Step 2: Simplify the Equation
Dividing both sides by k (assuming k≠0):
12X=16(X−2)
Expanding the right side:
12X=16X−32
Rearranging gives:
32=16X−12X
32=4X
X=8
Step 3: Calculate the Number of Men and Women
Now substituting X back:
- Number of Men = X=8
- Number of Women = X−2=6
Step 4: Work Done in 2 Days
Now, X2=82=4 men and (X−2)=6 women start the work.
Daily work done:
Work by Men in 1 day=4×3=12
Work by Women in 1 day=6×2=12
Total Work in 1 day=12+12=24
Work done in 2 days:
Total Work in 2 days=24×2=48
Step 5: Calculate Remaining Work
Total Work:
Total Work=12Xk=12×8k=96k
Remaining Work:
Remaining Work=96k−48=48k
Step 6: Work Required in 3 Days
To complete the remaining work in 3 days:
Work required per day=48k3=16k
Step 7: Determine How Many Women are Needed
Let Y be the number of women replacing men. The efficiency of Y women is:
Work done by Y women in 1 day=Y×2k
Setting the total work done in a day to 16k:
Y×2k=16k
Dividing both sides by 2k:
Y=8
Step 8: Calculate the Number of Women to Replace
Initially, there were 6 women. To find how many women need to be added:
Women to replace=Y−6=8−6=2
Final Answer
The number of women that should replace men to complete the remaining work in three days is 2.
---
Given:
- X men can complete the work in 4 days.
- (X−2) women can complete the same work in 8 days.
- The efficiency ratio of men to women is 3:2.
Total Work=Number of Men×Efficiency of Men×Time
=X×3k×4=12Xk
Total Work=Number of Women×Efficiency of Women×Time
=(X−2)×2k×8=16(X−2)k
12Xk=16(X−2)k
Dividing both sides by k (assuming k≠0):
12X=16(X−2)
Expanding the right side:
12X=16X−32
Rearranging gives:
32=16X−12X
32=4X
X=8
Now substituting X back:
- Number of Men = X=8
- Number of Women = X−2=6
Now, X2=82=4 men and (X−2)=6 women start the work.
Work by Men in 1 day=4×3=12
Work by Women in 1 day=6×2=12
Total Work in 1 day=12+12=24
Total Work in 2 days=24×2=48
Total Work:
Total Work=12Xk=12×8k=96k
Remaining Work=96k−48=48k
To complete the remaining work in 3 days:
Work required per day=48k3=16k
Let Y be the number of women replacing men. The efficiency of Y women is:
Work done by Y women in 1 day=Y×2k
Y×2k=16k
Dividing both sides by 2k:
Y=8
Initially, there were 6 women. To find how many women need to be added:
Women to replace=Y−6=8−6=2
The number of women that should replace men to complete the remaining work in three days is 2.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days
A6B5C4D2 - Question 2 - Select One
If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days
A6B5C4D2 - Question 3 - Select One
If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days
A6B5C4D2
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View Solution12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
View SolutionTwenty women together complete a piece of work in 16 days, 16 men together can complete the same work in 15 days. The ratio of the work ing capacity of a man to that of a woman is:
View SolutionTwenty women together complete a piece of work in 16 days, 16 men together can complete the same work in 15 days. The ratio of the work ing capacity of a man to that of a woman is:
View SolutionTwenty four men can complete a work in sixteen days. Thirty two women can complete the same work in twenty four days. Sixteen men and sixteen women started working and worked for 12 days. How many more. men are to be added to complete the remaining work in 2 days ?
View Solution