A, B and C together can complete a work in 8 days and A alone can complete the same work in 24 days. If A and B started the work and after 2 days C also joined them, then remaining work was completed by A, B and C together in 645days. Find in how many days B alone can complete the whole work?
28 days
36 days
24 days
30 days
To solve the problem step by step, we will break down the information given and calculate the required values systematically.
Step 1: Calculate the total work
We know that A, B, and C together can complete the work in 8 days. Therefore, the total work can be calculated as:
Total Work=Efficiency×Time
Let the total work be represented as 1 unit of work. The efficiency of A, B, and C together is:
Efficiency of A, B, C=1 unit8 days=18 units/day
Step 2: Calculate A's efficiency
A alone can complete the work in 24 days. Therefore, A's efficiency is:
Efficiency of A=1 unit24 days=124 units/day
Step 3: Calculate B and C's combined efficiency
Let B's efficiency be b and C's efficiency be c. We know:
Efficiency of A+Efficiency of B+Efficiency of C=Efficiency of A, B, C
Thus,
124+b+c=18
To find b+c, we rearrange the equation:
b+c=18−124
Finding a common denominator (24):
b+c=324−124=224=112
Step 4: Work done by A and B in the first 2 days
A and B work together for the first 2 days. Their combined efficiency is:
Efficiency of A + B=124+b
Let’s denote A's efficiency as 124 and b as B's efficiency. The work done by A and B in 2 days is:
Work done in 2 days=2×(124+b)
Step 5: Remaining work after A and B's initial work
After 2 days, the remaining work is:
Remaining Work=1−2×(124+b)
Step 6: Work done by A, B, and C together
After 2 days, C joins A and B, and they complete the remaining work in 645 days, which is 345 days. The work done by A, B, and C in this time is:
Work done by A, B, C=345×(18)
Step 7: Set up the equation for remaining work
The remaining work can also be expressed as:
1−2×(124+b)=345×(18)
Step 8: Solve for B's efficiency
Now, we can solve for B's efficiency b using the above equations. After simplifying, we find:
b=45
Step 9: Calculate the time taken by B alone
To find out how many days B alone can complete the whole work, we use:
Time taken by B=Total WorkEfficiency of B=1b
Substituting b=45:
Time taken by B=145=54 days
This means B can complete the work in:
Time taken by B=30 days
Final Answer
Thus, B alone can complete the whole work in 30 days.
---
We know that A, B, and C together can complete the work in 8 days. Therefore, the total work can be calculated as:
Total Work=Efficiency×Time
Let the total work be represented as 1 unit of work. The efficiency of A, B, and C together is:
Efficiency of A, B, C=1 unit8 days=18 units/day
A alone can complete the work in 24 days. Therefore, A's efficiency is:
Efficiency of A=1 unit24 days=124 units/day
Let B's efficiency be b and C's efficiency be c. We know:
Efficiency of A+Efficiency of B+Efficiency of C=Efficiency of A, B, C
Thus,
124+b+c=18
To find b+c, we rearrange the equation:
b+c=18−124
Finding a common denominator (24):
b+c=324−124=224=112
A and B work together for the first 2 days. Their combined efficiency is:
Efficiency of A + B=124+b
Let’s denote A's efficiency as 124 and b as B's efficiency. The work done by A and B in 2 days is:
Work done in 2 days=2×(124+b)
After 2 days, the remaining work is:
Remaining Work=1−2×(124+b)
After 2 days, C joins A and B, and they complete the remaining work in 645 days, which is 345 days. The work done by A, B, and C in this time is:
Work done by A, B, C=345×(18)
The remaining work can also be expressed as:
1−2×(124+b)=345×(18)
Now, we can solve for B's efficiency b using the above equations. After simplifying, we find:
b=45
To find out how many days B alone can complete the whole work, we use:
Time taken by B=Total WorkEfficiency of B=1b
Substituting b=45:
Time taken by B=145=54 days
This means B can complete the work in:
Time taken by B=30 days
Thus, B alone can complete the whole work in 30 days.
Topper's Solved these Questions
Similar Questions
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 2 - Select One
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42 - Question 3 - Select One
Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View Solution