Doubtnut Promotions Sticky

A is 40% more efficient than B and both together can complete a work in 938 days. If A work for first five days alone and remaining work complete by B, then find in how many days total work will be competed?

A

A)2012 days

B

B)16 days

C

C)1515 days

D

D)20 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for A is 40% more efficient than B and both together can complete a work in 9(3)/(8) days. If A work for first five days alone and remaining work complete by B, then find in how many days total work will be competed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 2 - Select One

    A is more efficient than B and they together can complete a work in 24 days. Had A done 50% of the work and then B, the remaining work, then the work would have been done in 50 days, B alone will complete 40% of the same work in:

    A16 days
    B24 days
    C21 days
    D20 days
  • Question 3 - Select One

    A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

    A17
    B19
    C19.5
    D21