A is 40% more efficient than B and both together can complete a work in 938 days. If A work for first five days alone and remaining work complete by B, then find in how many days total work will be competed?
A)2012 days
B)16 days
C)1515 days
D)20 days
The correct Answer is:A
Step by step video, text & image solution for A is 40% more efficient than B and both together can complete a work in 9(3)/(8) days. If A work for first five days alone and remaining work complete by B, then find in how many days total work will be competed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Mains Questions32videos
SPEED, TIME AND DISTANCE
- BOOK - ADDA247CHAPTER - SIMPLE INTEREST AND COMPOUND INTERESTEXERCISE - Previous Year Question30videos
SIMPLE INTEREST AND COMPOUND INTEREST
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS32videos
TIME AND WORK & PIPE AND CISTERN
Similar Questions
A is 40 % more efficient than B. If B can complete this work in 24 days. In how many days will both A and B complete this work ?
View SolutionA is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days - Question 2 - Select One
A is more efficient than B and they together can complete a work in 24 days. Had A done 50% of the work and then B, the remaining work, then the work would have been done in 50 days, B alone will complete 40% of the same work in:
A16 daysB24 daysC21 daysD20 days - Question 3 - Select One
A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
A17B19C19.5D21
A and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?
View SolutionA can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
View SolutionA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
View SolutionThe ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:
View SolutionA and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
View Solution