Doubtnut Promotions Sticky

The ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:

A

96 days

B

99 days

C

102 days

D

None of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the information given in the question and the video transcript.

Step 1: Determine the total efficiency of A, B, and C.
The efficiencies of A, B, and C are given in the ratio 7:5:8.

Let:
- Efficiency of A = 7x
- Efficiency of B = 5x
- Efficiency of C = 8x

The total efficiency when A, B, and C work together is:
Total Efficiency=7x+5x+8x=20x

Step 2: Calculate the total work.
It is given that A, B, and C can complete the work together in 42 days. Therefore, the total work can be calculated as:
Total Work=Total Efficiency×Number of Days
Total Work=20x×42=840x

Step 3: Calculate the work done by B and C in 21 days.
The combined efficiency of B and C is:
Efficiency of B and C=5x+8x=13x

The work done by B and C in 21 days is:
Work done by B and C=Efficiency of B and C×Number of Days
Work done by B and C=13x×21=273x

Step 4: Calculate the remaining work.
The remaining work after B and C have worked for 21 days is:
Remaining Work=Total WorkWork done by B and C
Remaining Work=840x273x=567x

Step 5: Determine how long A takes to complete the remaining work.
A's efficiency is 7x. The time taken by A to complete the remaining work is:
Time taken by A=Remaining WorkEfficiency of A
Time taken by A=567x7x=81 days

Step 6: Calculate the total time taken to complete the work.
The total time taken to complete the work is the time taken by B and C plus the time taken by A:
Total Time=Time taken by B and C+Time taken by A
Total Time=21 days+81 days=102 days

Final Answer:
The whole work was completed in 102 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?

    A18 days
    B24 days
    C21 days
    D15 days
  • Question 2 - Select One

    The ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
    A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?

    A60
    B63
    C56
    D49
  • Question 3 - Select One

    The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :

    A54 days
    B45 days
    C60 days
    D85 days