The ratio of the efficiencies of A, B and C is 7:5:8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining work was completed by A alone. The whole work was completed in:
96 days
99 days
102 days
None of these
The correct Answer is:C
To solve the problem step by step, we will follow the information given in the question and the video transcript.
Step 1: Determine the total efficiency of A, B, and C.
The efficiencies of A, B, and C are given in the ratio 7:5:8.
Let:
- Efficiency of A = 7x
- Efficiency of B = 5x
- Efficiency of C = 8x
The total efficiency when A, B, and C work together is:
Total Efficiency=7x+5x+8x=20x
Step 2: Calculate the total work.
It is given that A, B, and C can complete the work together in 42 days. Therefore, the total work can be calculated as:
Total Work=Total Efficiency×Number of Days
Total Work=20x×42=840x
Step 3: Calculate the work done by B and C in 21 days.
The combined efficiency of B and C is:
Efficiency of B and C=5x+8x=13x
The work done by B and C in 21 days is:
Work done by B and C=Efficiency of B and C×Number of Days
Work done by B and C=13x×21=273x
Step 4: Calculate the remaining work.
The remaining work after B and C have worked for 21 days is:
Remaining Work=Total Work−Work done by B and C
Remaining Work=840x−273x=567x
Step 5: Determine how long A takes to complete the remaining work.
A's efficiency is 7x. The time taken by A to complete the remaining work is:
Time taken by A=Remaining WorkEfficiency of A
Time taken by A=567x7x=81 days
Step 6: Calculate the total time taken to complete the work.
The total time taken to complete the work is the time taken by B and C plus the time taken by A:
Total Time=Time taken by B and C+Time taken by A
Total Time=21 days+81 days=102 days
Final Answer:
The whole work was completed in 102 days.
The efficiencies of A, B, and C are given in the ratio 7:5:8.
- Efficiency of A = 7x
- Efficiency of B = 5x
- Efficiency of C = 8x
Total Efficiency=7x+5x+8x=20x
It is given that A, B, and C can complete the work together in 42 days. Therefore, the total work can be calculated as:
Total Work=Total Efficiency×Number of Days
Total Work=20x×42=840x
The combined efficiency of B and C is:
Efficiency of B and C=5x+8x=13x
Work done by B and C=Efficiency of B and C×Number of Days
Work done by B and C=13x×21=273x
The remaining work after B and C have worked for 21 days is:
Remaining Work=Total Work−Work done by B and C
Remaining Work=840x−273x=567x
A's efficiency is 7x. The time taken by A to complete the remaining work is:
Time taken by A=Remaining WorkEfficiency of A
Time taken by A=567x7x=81 days
The total time taken to complete the work is the time taken by B and C plus the time taken by A:
Total Time=Time taken by B and C+Time taken by A
Total Time=21 days+81 days=102 days
The whole work was completed in 102 days.
Topper's Solved these Questions
Similar Questions
The efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?View SolutionTo do a certain work the ratio of the efficincies of A, B and C is 7:5:6. Working together they can complete the same work in 35 days. B and C work together for 21 days. The remaining work will be completed by A alone in:
View Solution
Knowledge Check
- Question 1 - Select One
The ratio of the efficiencies of A, B and C is 3: 5:1. Working together, they can complete a piece of work in 5 days. A and B work together for 3 days. The remaining work will be completed by C alone in?
A18 daysB24 daysC21 daysD15 days - Question 2 - Select One
The ratio of the efficiencies of A, B and C is 7:5:4. Working together, they can finish work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone:
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 4 है | एक साथ कार्य करते हुए, वे किसी कार्य को 35 दिनों में समाप्त कर सकते हैं | A और B एक साथ 28 दिनों तक कार्य करते हैं | C शेष कार्य कितने दिनों में पूरा करेगा ?A60B63C56D49 - Question 3 - Select One
The ratio of the efficiencies of A, B and C to do a certain work is 7:3:5. Working together, they can complete the work in 21 days. A and C worked together for 5 days. The remaining work will be completed by B alone in :
A54 daysB45 daysC60 daysD85 days
The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:
View SolutionThe ratio of the efficiencies of A, B, C is 7:5:4. Working togehter, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone.
View SolutionThe ratio of the efficiencies of A, B and C is 4 : 5 : 3. Working together, they can complete that work in 25 days. A and C together will complete 35% of that work in:
A, B तथा C की कार्य क्षमता का अनुपात 4 : 5 : 3 है | एक साथ कार्य करते हुए वे 25 दिनों में कार्य पूरा कर लेते हैं | इस कार्य का 35% भाग A और C कितने दिनों में पूरा करेंगे ?View SolutionThe ratio of the efficiencies of A, B and C is 2 : 5 : 3. Working together, they can complete a work in 27 days. B and C together can complete 4/9th part of that work in:
A, B और C की कार्य क्षमता का अनुपात 2 : 5 : 3 है | एक साथ कार्य करते हुए, वे किसी कार्य को 27 दिन में पूरा कर सकते हैं | B और C एक साथ उस कार्य के 4/9 भाग को कितने दिनों में पूरा करेंगे ?View SolutionTo do a certain work, the ratio of efficiency of A to that of B is 3:7.Working together, they can complete the work in 1012 days. They work together for 8 days. 60% of the remaining work will be completed by A alone in :
किसी कार्य को करने में, A की कार्य क्षमता तथा 8 की कार्य क्षमता का अनुपात 3: 7 है | एक साथ कार्य करते हुए, वे इस कार्य को 1012 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य का 60% हिस्सा A अकेले कितने दिनों में पूरा करेगा ?View Solution