X and Y can complete a work in 12 days together. After working 4 days together, Y left the job and a third person Z, whose efficiency is 5/3 of efficiency of X, joins the work. The whole work is completed in 8 days. In how many days, Y can complete the whole work alone?

A

36

B

48

C

24

D

18

Text Solution
Verified by Experts

The correct Answer is:B

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?

    A24 days
    B15 days
    C8 days
    D18 days
  • Question 2 - Select One

    A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?

    A27
    B24
    C36
    D42
  • Question 3 - Select One

    X' can complete a work in 40 days while Y is 20% more effi-
    cient then 'X' .'Y' worked for 8 days and lift, remaining work is
    completed by 'Z' in 20 days. Find in how many days 'Z' can ltbegt complete the whole work alone?

    A27 days
    B21 days
    C18 days
    D26 days