Ais twice as efficient as B.B started the work and after 4
days A joins B and the total work was complete in 9 days
then B can complete whole work alone in :
9.5 days
10 days
19 days
38 days
The correct Answer is:(c)
A twice ecficient, so if B taken 2xdays to complete a
work, then A taken x days to complete that work.
Now, B worked for 9 days and A for (9−4)=5 days
S0,1×5+12x×9=1
2x=19
So, B is 19 days
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 120 days and B can do it in 150 days. The work together for 20 days. Then, B leave and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it, if he works alone?
View SolutionA can complete a piece of work in 25 days. After working for 5 days, remaining work is completed in 15 days with the help of B. Then B can complete the whole work in how many days?
View Solution
Knowledge Check
- Question 1 - Select One
A works twice as fast as B and B works twice as fast as C. If A and B together complete a work in 4 days, then C alone can complete the work in :
A6B8C24D12 - Question 2 - Select One
A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30 - Question 3 - Select One
A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
A230 daysB225 daysC240 daysD220 days
A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionA, B and C can alone complete a work in 15, 25 and 30 days
respectively. A and B started the work and after some days A
is replaced by C. Now the work is completed in a further of
6 4/11 days. How much of the total work did B did ?View SolutionA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
View Solution