Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take 163 more number of days than A, B and C take together. If A, B and C all have work together till the completion of the work and B has received Rs. 120 out of the total earning of Rs. 450, then in how many days did A, B and C together complete the whole work?
10
6
8
12
The correct Answer is:C
Topper's Solved these Questions
- BOOK - GAGAN PRATAP CHAPTER - TIME & WORKEXERCISE - TIME & WORK (SHEET-3)23videos
TIME & WORK
- BOOK - GAGAN PRATAP CHAPTER - TIME & WORKEXERCISE - TIME & WORK (SHEET-3)23videos
TIME & WORK
- BOOK - GAGAN PRATAP CHAPTER - SURDS & INDICESEXERCISE - Surds & Indices (Sheet-2)64videos
SURDS & INDICES
- BOOK - GAGAN PRATAP CHAPTER - TIME SPEED & DISTANCEEXERCISE - MULTIPLE CHOICE QUESTIONS143videos
TIME SPEED & DISTANCE
Similar Questions
Acan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
View SolutionA piece of work can be completed in 18 days if A and B work together, in 24 days if B and C work together and in 36 days if A and C work together. The number of days required if all the three work together is
View Solution
Knowledge Check
- Question 1 - Select One
Working together B and C take 50% more number of days than A,B and C together take and A and B working together, take 83 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work?
A10B6C4D2 - Question 2 - Select One
Working together B and C take 50% more number of days than A,B and C together take and A and B working together, take 83 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work?
A10B6C4D2 - Question 3 - Select One
A and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?
A8B16C12D15
A and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A and C together, complete the work ?View SolutionA takes 6 hours more than (A + B + C) together to complete a work. B takes 1 hours more than (A + B + C) together to complete a work. C takes twice as (A + B + C) together to complete a work. In how many days will A and B together complete this work ?
View SolutionA is three times efficient than B. If A takes 24 days less than B to complete the work, then find in how many days A and B together can complete the whole work.
View SolutionA and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
View SolutionA and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
View Solution