Doubtnut Promotions Sticky

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take 163 more number of days than A, B and C take together. If A, B and C all have work together till the completion of the work and B has received Rs. 120 out of the total earning of Rs. 450, then in how many days did A, B and C together complete the whole work?

A

10

B

6

C

8

D

12

Text Solution
Verified by Experts

The correct Answer is:C

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Working together B and C take 50% more number of days than A,B and C together take and A and B working together, take 83 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work?

    A10
    B6
    C4
    D2
  • Question 2 - Select One

    Working together B and C take 50% more number of days than A,B and C together take and A and B working together, take 83 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work?

    A10
    B6
    C4
    D2
  • Question 3 - Select One

    A and B together complete a work in 20 days, B and C together complete same work in 30 days, C and A together complete the same work 24 days, In how many days A, B and C together can complete the same work?

    A8
    B16
    C12
    D15