The contract of a construction job specifies a penalty or delay of completion beyond a certain date as follows : Rs 200 for the first day , Rs 250 for the second day , Rs 300 for the third day and so on . How much does a delay of 30 days cost the contractor ?
The correct Answer is:Rs 27,750
Topper's Solved these Questions
- ARITHMETIC PROGRESSION BOOK - OSWAL PUBLICATIONCHAPTER - ARITHMETIC PROGRESSION EXERCISE - CASE BASED QUESTIONS
5 Videos
- AREAS RELATED TO CIRCLES BOOK - OSWAL PUBLICATIONCHAPTER - AREAS RELATED TO CIRCLES EXERCISE - CASE- Based MCQs (III)
5 Videos
- ARITHMETIC PROGRESSIONS BOOK - OSWAL PUBLICATIONCHAPTER - ARITHMETIC PROGRESSIONS EXERCISE - CASE - BASED MCQs
15 Videos
Similar Questions
A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day, Rs. 250 for second day, Rs. 300 for thirdday and so on. If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?
View SolutionA boy spends Rs. 10 on first day, Rs. 20 on second day, Rs. 40 on third day and so on. Find how much, in all, will he spend in 12 days ?
View SolutionLalit earns Rs. x per day and spends Rs. y per day. How much does he save in 30 days?
View SolutionDaya gets pocket money from his father every day. Out of the pocket money, he saves Rs 2.75 on first day, Rs 3.00 on second day, Rs 3.25 on third day and so on. Find:
the amount saved by Daya on 30th day
View SolutionDaya gets pocket money from his father every day. Out of the pocket money, he saves Rs 2.75 on first day, Rs 3.00 on second day, Rs 3.25 on third day and so on. Find:
the total amount saved by him in 30 days.
View Solution