P and Q each working alone can do a work in 10 days and 15 days, respectively. They started the work together but Qleft after sometime and Pfinished the remaining work in 5 days. After how many days from the start did Q leave?
3 days
6 days
2 days
4 days
To solve the problem step by step, we will first determine the work rates of P and Q, then find out how long they worked together before Q left, and finally calculate the remaining work completed by P after Q left.
Step 1: Determine the work rates of P and Q
- P can complete the work in 10 days. Therefore, the work rate of P is:
Work rate of P=1 work10 days=0.1 work/day
- Q can complete the work in 15 days. Therefore, the work rate of Q is:
Work rate of Q=1 work15 days=115 work/day≈0.0667 work/day
Step 2: Calculate the combined work rate of P and Q
When P and Q work together, their combined work rate is:
Combined work rate=Work rate of P+Work rate of Q=0.1+115
To add these, we convert 0.1 to a fraction:
0.1=110
Now, finding a common denominator (which is 30):
110=330,115=230
Thus,
Combined work rate=330+230=530=16 work/day
Step 3: Determine the total work done before Q leaves
Let x be the number of days they worked together before Q left. The amount of work done in x days by both P and Q is:
Work done=Combined work rate×x=16×x
Step 4: Calculate the remaining work done by P after Q leaves
After Q leaves, P finishes the remaining work in 5 days. The amount of work P can do in 5 days is:
Work done by P in 5 days=Work rate of P×5=0.1×5=510=12 work
Step 5: Set up the equation for total work
The total work is 1 (the whole job), so we can set up the equation:
Work done by both+Work done by P=1
Substituting the expressions we found:
x6+12=1
Step 6: Solve for x
First, convert 12 to a fraction with a denominator of 6:
12=36
Now, substituting this into the equation:
x6+36=1
Subtract 36 from both sides:
x6=1−36=36=12
Multiply both sides by 6:
x=3
Conclusion
Q left after 3 days from the start.
- P can complete the work in 10 days. Therefore, the work rate of P is:
Work rate of P=1 work10 days=0.1 work/day
- Q can complete the work in 15 days. Therefore, the work rate of Q is:
Work rate of Q=1 work15 days=115 work/day≈0.0667 work/day
When P and Q work together, their combined work rate is:
Combined work rate=Work rate of P+Work rate of Q=0.1+115
To add these, we convert 0.1 to a fraction:
0.1=110
Now, finding a common denominator (which is 30):
110=330,115=230
Thus,
Combined work rate=330+230=530=16 work/day
Let x be the number of days they worked together before Q left. The amount of work done in x days by both P and Q is:
Work done=Combined work rate×x=16×x
After Q leaves, P finishes the remaining work in 5 days. The amount of work P can do in 5 days is:
Work done by P in 5 days=Work rate of P×5=0.1×5=510=12 work
The total work is 1 (the whole job), so we can set up the equation:
Work done by both+Work done by P=1
Substituting the expressions we found:
x6+12=1
First, convert 12 to a fraction with a denominator of 6:
12=36
Now, substituting this into the equation:
x6+36=1
Subtract 36 from both sides:
x6=1−36=36=12
Multiply both sides by 6:
x=3
Q left after 3 days from the start.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View Solution
Knowledge Check
A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?
A3B5C7D9Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?
A5 daysB4 daysC6 daysD3 daysA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
A2 daysB3 daysC1 dayDNone of these
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B cand o a pieces of work in 10 days and 15 days, respectively. They started the work together but B left after sometime and A finished the work in 5 days. After how many days (from the start) did B leave?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
View Solution