Doubtnut Promotions Sticky

P and Q each working alone can do a work in 10 days and 15 days, respectively. They started the work together but Qleft after sometime and Pfinished the remaining work in 5 days. After how many days from the start did Q leave?

A

3 days

B

6 days

C

2 days

D

4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work rates of P and Q, then find out how long they worked together before Q left, and finally calculate the remaining work completed by P after Q left.

Step 1: Determine the work rates of P and Q
- P can complete the work in 10 days. Therefore, the work rate of P is:
Work rate of P=1 work10 days=0.1 work/day
- Q can complete the work in 15 days. Therefore, the work rate of Q is:
Work rate of Q=1 work15 days=115 work/day0.0667 work/day

Step 2: Calculate the combined work rate of P and Q
When P and Q work together, their combined work rate is:
Combined work rate=Work rate of P+Work rate of Q=0.1+115
To add these, we convert 0.1 to a fraction:
0.1=110
Now, finding a common denominator (which is 30):
110=330,115=230
Thus,
Combined work rate=330+230=530=16 work/day

Step 3: Determine the total work done before Q leaves
Let x be the number of days they worked together before Q left. The amount of work done in x days by both P and Q is:
Work done=Combined work rate×x=16×x

Step 4: Calculate the remaining work done by P after Q leaves
After Q leaves, P finishes the remaining work in 5 days. The amount of work P can do in 5 days is:
Work done by P in 5 days=Work rate of P×5=0.1×5=510=12 work

Step 5: Set up the equation for total work
The total work is 1 (the whole job), so we can set up the equation:
Work done by both+Work done by P=1
Substituting the expressions we found:
x6+12=1

Step 6: Solve for x
First, convert 12 to a fraction with a denominator of 6:
12=36
Now, substituting this into the equation:
x6+36=1
Subtract 36 from both sides:
x6=136=36=12
Multiply both sides by 6:
x=3

Conclusion
Q left after 3 days from the start.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?

    A3
    B5
    C7
    D9
  • Question 2 - Select One

    Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?

    A5 days
    B4 days
    C6 days
    D3 days
  • Question 3 - Select One

    A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

    A2 days
    B3 days
    C1 day
    DNone of these