A and B cand o a pieces of work in 10 days and 15 days, respectively. They started the work together but B left after sometime and A finished the work in 5 days. After how many days (from the start) did B leave?
To solve the problem step by step, we can follow these calculations:
Step 1: Determine the Work Rates of A and B
- A can complete the work in 10 days, so A's work rate is:
Work rate of A=1 work10 days=0.1 work/day
- B can complete the work in 15 days, so B's work rate is:
Work rate of B=1 work15 days=115 work/day≈0.0667 work/day
Step 2: Calculate the Total Work
- To make calculations easier, we can assume the total work is 60 units (the LCM of 10 and 15).
- Therefore, A's efficiency is:
Efficiency of A=60 units10 days=6 units/day
- And B's efficiency is:
Efficiency of B=60 units15 days=4 units/day
Step 3: Calculate Work Done by A and B Together
- Let’s denote the number of days B worked as x.
- In x days, A and B together will complete:
Work done by A and B in x days=(6+4)×x=10x units
Step 4: Work Done by A Alone After B Leaves
- After B leaves, A works alone for 5 days. The work done by A in 5 days is:
Work done by A alone=6×5=30 units
Step 5: Set Up the Equation for Total Work
- The total work done by A and B together plus the work done by A alone must equal the total work:
10x+30=60
Step 6: Solve for x
- Rearranging the equation gives:
10x=60−30
10x=30
x=3010=3
Conclusion
- B worked for 3 days before leaving.
- A can complete the work in 10 days, so A's work rate is:
Work rate of A=1 work10 days=0.1 work/day
- B can complete the work in 15 days, so B's work rate is:
Work rate of B=1 work15 days=115 work/day≈0.0667 work/day
- To make calculations easier, we can assume the total work is 60 units (the LCM of 10 and 15).
- Therefore, A's efficiency is:
Efficiency of A=60 units10 days=6 units/day
- And B's efficiency is:
Efficiency of B=60 units15 days=4 units/day
- Let’s denote the number of days B worked as x.
- In x days, A and B together will complete:
Work done by A and B in x days=(6+4)×x=10x units
- After B leaves, A works alone for 5 days. The work done by A in 5 days is:
Work done by A alone=6×5=30 units
- The total work done by A and B together plus the work done by A alone must equal the total work:
10x+30=60
- Rearranging the equation gives:
10x=60−30
10x=30
x=3010=3
- B worked for 3 days before leaving.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 130videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?
A3B5C7D9 - Question 2 - Select One
Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?
A5 daysB4 daysC6 daysD3 days - Question 3 - Select One
A and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
A5 daysB10 daysC11 daysD6 days
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View Solution