Doubtnut Promotions Sticky

A job was wrongly estimated to be completed in 10 days by By deploying 3 extra machines, the job was completed in 12 days. If only 1 extra machine was used, the no. of days more than one additional machine that estimated it has taken to complete the job will be ?

Video Solution
|
Answer

Step by step video solution for A job was wrongly estimated to be completed in 10 days by By deploying 3 extra machines, the job was completed in 12 days. If only 1 extra machine was used, the no. of days more than one additional machine that estimated it has taken to complete the job will be ? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :

    A10
    B8
    C16
    D32
  • Question 2 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A30
    B40
    C25
    D50
  • Question 3 - Select One

    A man take 80 days to complete a job. To complete this job, 4 men, 8 women and 4 machines take 5 days. Alternatively, 4 men, 1, women and 2 machines take 10 days to complete the job. Find the time taken by a women to complete the job (in says)

    A90
    B100
    C105
    D120