Doubtnut Promotions Sticky

A job was wrongly estimated to be completed in 10 days by x machines. By deploying 3 extra was completed in 12 days. If only one additional machine was used, the no. of has taken to complete the job will be days more than that estimated it

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A job was wrongly estimated to be completed in 10 days by x machines. By deploying 3 extra was completed in 12 days. If only one additional machine was used, the no. of has taken to complete the job will be days more than that estimated it by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.

Updated on:21/07/2023

Similar Practice Problems

  • Question 1 - Select One

    16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :

    A10
    B8
    C16
    D32
  • Question 1 - Select One

    X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

    A10 days
    B12 days
    C15 days
    D18 days
  • Question 1 - Select One

    If 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.

    A3
    B10
    C12
    D4
  • Question 1 - Select One

    16 men finished one-third work in 6 days. The number of additional men are required to complete the remaining job in next 6 days:

    A10
    B8
    C16
    D32

Similar Questions