A job was wrongly estimated to be completed in 10 days by x machines. By deploying 3 extra was completed in 12 days. If only one additional machine was used, the no. of has taken to complete the job will be days more than that estimated it
Step by step video & image solution for A job was wrongly estimated to be completed in 10 days by x machines. By deploying 3 extra was completed in 12 days. If only one additional machine was used, the no. of has taken to complete the job will be days more than that estimated it by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.
Updated on:21/07/2023Similar Questions
A job was wrongly estimated to be completed in 10 days by By deploying 3 extra machines, the job was completed in 12 days. If only 1 extra machine was used, the no. of days more than one additional machine that estimated it has taken to complete the job will be ?
View SolutionA job was wrongly estimated to be completed in 10 days by By deploying 3 extra machines, the job was completed in 12 days. If only 1 extra machine was used, the no. of days more than one additional machine that estimated it has taken to complete the job will be ?
View Solution
Knowledge Check
16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :
A10B8C16D32X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
A10 daysB12 daysC15 daysD18 daysIf 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.
A3B10C12D4
Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6(23) days. 'Y' alone can complete the job on
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionFifteen men take 10 days to complete a job working 12hours a day. How many hours in a day should 10 men work to complete the same job in 20 days?
View Solution16 men finished one-third work in 6 days. The number of additional men are required to complete the remaining job in next 6 days:
View Solution