Doubtnut Promotions Sticky

A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?

A

4/3 days

B

3 days

C

3 days

D

12 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem of how many days the company will take to complete the job if all machines A, B, and C are used simultaneously, we can follow these steps:

Step 1: Determine the work done by each machine in one day.
- Machine A can complete the job in 3 days. Therefore, the work done by A in one day is:
Work by A in one day=13 of the job

- Machine B can complete the job in 4 days. Therefore, the work done by B in one day is:
Work by B in one day=14 of the job

- Machine C can complete the job in 6 days. Therefore, the work done by C in one day is:
Work by C in one day=16 of the job

Step 2: Calculate the total work done by all machines in one day.
To find the total work done by all machines in one day, we add the work done by each machine:
Total work in one day=Work by A+Work by B+Work by C
=13+14+16

Step 3: Find a common denominator and add the fractions.
The least common multiple (LCM) of 3, 4, and 6 is 12. We convert each fraction:
13=412,14=312,16=212
Now, add them together:
Total work in one day=412+312+212=4+3+212=912=34 of the job

Step 4: Calculate the time taken to complete the job.
If the machines together complete 34 of the job in one day, then the time taken to complete the entire job (1 job) is:
Time=1 job34 job/day=43 days

Final Answer:
The company will take 43 days to complete the job if all machines are used simultaneously.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A company has a job to prepare certain no. of cans and there are three machines A, B & C for this job. A can complete the job in 3 days, B can complete the job in 4 days and C can complete the job in 6 days. How many days the company will take to complete job if all the machines are used simultaneously?
    A)4 days
    B)4/3 days
    C)3 days
    D)12 days

    A4 days
    B4/3 days
    C3 days
    D12 days
  • Question 2 - Select One

    22 men can complete a job in 16days. In how many days, will 32 men complete that job?

    A14
    B12
    C16
    D11
  • Question 3 - Select One

    X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

    A10 days
    B12 days
    C15 days
    D18 days