A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?
4/3 days
3 days
3 days
12 days
The correct Answer is:C
To solve the problem of how many days the company will take to complete the job if all machines A, B, and C are used simultaneously, we can follow these steps:
Step 1: Determine the work done by each machine in one day.
- Machine A can complete the job in 3 days. Therefore, the work done by A in one day is:
Work by A in one day=13 of the job
- Machine B can complete the job in 4 days. Therefore, the work done by B in one day is:
Work by B in one day=14 of the job
- Machine C can complete the job in 6 days. Therefore, the work done by C in one day is:
Work by C in one day=16 of the job
Step 2: Calculate the total work done by all machines in one day.
To find the total work done by all machines in one day, we add the work done by each machine:
Total work in one day=Work by A+Work by B+Work by C
=13+14+16
Step 3: Find a common denominator and add the fractions.
The least common multiple (LCM) of 3, 4, and 6 is 12. We convert each fraction:
13=412,14=312,16=212
Now, add them together:
Total work in one day=412+312+212=4+3+212=912=34 of the job
Step 4: Calculate the time taken to complete the job.
If the machines together complete 34 of the job in one day, then the time taken to complete the entire job (1 job) is:
Time=1 job34 job/day=43 days
Final Answer:
The company will take 43 days to complete the job if all machines are used simultaneously.
---
- Machine A can complete the job in 3 days. Therefore, the work done by A in one day is:
Work by A in one day=13 of the job
- Machine B can complete the job in 4 days. Therefore, the work done by B in one day is:
Work by B in one day=14 of the job
Work by C in one day=16 of the job
To find the total work done by all machines in one day, we add the work done by each machine:
Total work in one day=Work by A+Work by B+Work by C
=13+14+16
The least common multiple (LCM) of 3, 4, and 6 is 12. We convert each fraction:
13=412,14=312,16=212
Now, add them together:
Total work in one day=412+312+212=4+3+212=912=34 of the job
If the machines together complete 34 of the job in one day, then the time taken to complete the entire job (1 job) is:
Time=1 job34 job/day=43 days
The company will take 43 days to complete the job if all machines are used simultaneously.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A company has a job to prepare certain no. of cans and there are three machines A, B & C for this job. A can complete the job in 3 days, B can complete the job in 4 days and C can complete the job in 6 days. How many days the company will take to complete job if all the machines are used simultaneously?
A)4 days
B)4/3 days
C)3 days
D)12 daysA4 daysB4/3 daysC3 daysD12 days22 men can complete a job in 16days. In how many days, will 32 men complete that job?
A14B12C16D11X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
A10 daysB12 daysC15 daysD18 days
P can do a job in 12 days and Q can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionA can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6(23) days. 'Y' alone can complete the job on
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View Solution