Doubtnut Promotions Sticky

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Video Solution
Text Solution
Verified by Experts

The correct Answer is:25 days


Suppose the work is completed in n days. Since 4 workers dropped every day except the first day, the total amount of work done in n days is the sum of n terms of an A.P. with first term 150 and common difference -4.
Total amount of work done
=n2[2×150+(n1)×(4)]=n(1522n)
Had the workers not dropped, the work would have finished in (n-8) days with 150 workers working each day. Therefore, the total amount of work done in n days is 150 (n-8).
n(152-2n)=150(n-8)
n2n600=0
(n25)(n+24)=0
n=25
Thus, the work is completed in 25 days

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • Question 2 - Select One

    56 workers canfinish a piece of work in 14 days. If the work
    is to be completed in 8 days, then how many extra workers
    are required ?

    A36
    B48
    C44
    D42
  • Question 3 - Select One

    8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?

    A2
    B3
    C4
    D5