15 men and 25 men women can dig an area of 880m2 in 8 days. In how many days can 20 men adn 12 women dig an area of 1040 m2 , if each man can dig twice the area of the each women can dig in the same amount of time?
6 days
8 days
10 days
2 days
The correct Answer is:C
To solve the problem step by step, we will first establish the relationship between men and women in terms of work done, and then apply that to find the number of days required for the second group to complete their task.
Step 1: Understand the work done by men and women
Given:
- 15 men and 25 women can dig 880 m² in 8 days.
Let’s find the total work done in terms of man-days.
Total work = 880 m²
Total man-days = Number of workers × Number of days = (15 + 25) workers × 8 days = 40 workers × 8 days = 320 man-days.
Step 2: Calculate the work done per man and per woman
Since we know that each man can dig twice the area of each woman, we can denote:
- Work done by 1 woman in 1 day = W
- Work done by 1 man in 1 day = 2W
Now, we can express the total work done in terms of W:
- Total work done by 15 men and 25 women in 1 day:
- Work by men = 15 men × 2W = 30W
- Work by women = 25 women × W = 25W
- Total work in 1 day = 30W + 25W = 55W
Step 3: Relate total work to W
Since they complete 880 m² in 8 days:
- Total work in 8 days = 8 days × 55W = 440W
- Therefore, 440W = 880 m² → W = 2 m² (work done by 1 woman in 1 day).
Step 4: Calculate work done by men
Now, since W = 2 m²:
- Work done by 1 man in 1 day = 2W = 4 m².
Step 5: Calculate total work done by 20 men and 12 women
Now, we need to find out how many days it takes for 20 men and 12 women to dig 1040 m².
- Work done by 20 men in 1 day = 20 men × 4 m²/man = 80 m².
- Work done by 12 women in 1 day = 12 women × 2 m²/woman = 24 m².
- Total work done by 20 men and 12 women in 1 day = 80 m² + 24 m² = 104 m².
Step 6: Calculate the number of days required to dig 1040 m²
Now, we can find the number of days (D) required to dig 1040 m²:
- Total work = 1040 m²
- Work done in 1 day = 104 m²
Thus, the number of days required:
D=TotalworkWorkdonein1day=1040m²104m²/day=10days.
Final Answer
The number of days required for 20 men and 12 women to dig 1040 m² is 10 days.
---
Given:
- 15 men and 25 women can dig 880 m² in 8 days.
Total man-days = Number of workers × Number of days = (15 + 25) workers × 8 days = 40 workers × 8 days = 320 man-days.
Since we know that each man can dig twice the area of each woman, we can denote:
- Work done by 1 woman in 1 day = W
- Work done by 1 man in 1 day = 2W
- Total work done by 15 men and 25 women in 1 day:
- Work by men = 15 men × 2W = 30W
- Work by women = 25 women × W = 25W
- Total work in 1 day = 30W + 25W = 55W
Since they complete 880 m² in 8 days:
- Total work in 8 days = 8 days × 55W = 440W
- Therefore, 440W = 880 m² → W = 2 m² (work done by 1 woman in 1 day).
Now, since W = 2 m²:
- Work done by 1 man in 1 day = 2W = 4 m².
Now, we need to find out how many days it takes for 20 men and 12 women to dig 1040 m².
- Work done by 12 women in 1 day = 12 women × 2 m²/woman = 24 m².
- Total work done by 20 men and 12 women in 1 day = 80 m² + 24 m² = 104 m².
Now, we can find the number of days (D) required to dig 1040 m²:
- Total work = 1040 m²
- Work done in 1 day = 104 m²
D=TotalworkWorkdonein1day=1040m²104m²/day=10days.
The number of days required for 20 men and 12 women to dig 1040 m² is 10 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 219videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
Knowledge Check
- Question 1 - Select One
Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it ?
A10B15C20D25 - Question 2 - Select One
12 men can reap a field in 25 days. In how many days can 20 men reap the same field?
A65 daysB35 daysC15 daysD25 days - Question 3 - Select One
If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?
A38B32C40D35
12 men can reap a field in 25 days. In how many days can 20 men reap the same field.
View Solution6 men and 8 women can do a job in 10'days. In how many days can 3 men and 4 women finish the same job working together?
View SolutionFive men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it ?
View SolutionIf 3 men and 4 women can build a wall in 43 days , in how many days can 7 men and 5 women build this wall ?
View SolutionIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
View Solution