Doubtnut Promotions Sticky

15 men and 25 men women can dig an area of 880m2 in 8 days. In how many days can 20 men adn 12 women dig an area of 1040 m2 , if each man can dig twice the area of the each women can dig in the same amount of time?

A

6 days

B

8 days

C

10 days

D

2 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first establish the relationship between men and women in terms of work done, and then apply that to find the number of days required for the second group to complete their task.

Step 1: Understand the work done by men and women
Given:
- 15 men and 25 women can dig 880 m² in 8 days.

Let’s find the total work done in terms of man-days.

Total work = 880 m²
Total man-days = Number of workers × Number of days = (15 + 25) workers × 8 days = 40 workers × 8 days = 320 man-days.

Step 2: Calculate the work done per man and per woman
Since we know that each man can dig twice the area of each woman, we can denote:
- Work done by 1 woman in 1 day = W
- Work done by 1 man in 1 day = 2W

Now, we can express the total work done in terms of W:
- Total work done by 15 men and 25 women in 1 day:
- Work by men = 15 men × 2W = 30W
- Work by women = 25 women × W = 25W
- Total work in 1 day = 30W + 25W = 55W

Step 3: Relate total work to W
Since they complete 880 m² in 8 days:
- Total work in 8 days = 8 days × 55W = 440W
- Therefore, 440W = 880 m² → W = 2 m² (work done by 1 woman in 1 day).

Step 4: Calculate work done by men
Now, since W = 2 m²:
- Work done by 1 man in 1 day = 2W = 4 m².

Step 5: Calculate total work done by 20 men and 12 women
Now, we need to find out how many days it takes for 20 men and 12 women to dig 1040 m².

- Work done by 20 men in 1 day = 20 men × 4 m²/man = 80 m².
- Work done by 12 women in 1 day = 12 women × 2 m²/woman = 24 m².
- Total work done by 20 men and 12 women in 1 day = 80 m² + 24 m² = 104 m².

Step 6: Calculate the number of days required to dig 1040 m²
Now, we can find the number of days (D) required to dig 1040 m²:
- Total work = 1040 m²
- Work done in 1 day = 104 m²

Thus, the number of days required:
D=TotalworkWorkdonein1day=1040m²104m²/day=10days.

Final Answer
The number of days required for 20 men and 12 women to dig 1040 m² is 10 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it ?

    A10
    B15
    C20
    D25
  • Question 2 - Select One

    12 men can reap a field in 25 days. In how many days can 20 men reap the same field?

    A65 days
    B35 days
    C15 days
    D25 days
  • Question 3 - Select One

    If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?

    A38
    B32
    C40
    D35