Doubtnut Promotions Sticky

A, B and C can complete a piece of work in 10 days, 20 days and 25 days, respectively. If they tak 40 days to complete a piece of work, then in how many days can C alone complete the work ?

A

65 days

B

76 days

C

95 days

D

190 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 20 days, so B's work rate is 120 of the work per day.
- C can complete the work in 25 days, so C's work rate is 125 of the work per day.

Step 2: Calculate the combined work rate of A, B, and C
The combined work rate of A, B, and C is:
Combined work rate=110+120+125

Step 3: Find the LCM of the denominators
The denominators are 10, 20, and 25. The least common multiple (LCM) of these numbers is 100.

Step 4: Convert each fraction to have a common denominator
- 110=10100
- 120=5100
- 125=4100

Step 5: Add the fractions
Combined work rate=10100+5100+4100=19100

Step 6: Calculate the time taken by A, B, and C together to complete the work
If A, B, and C work together, they can complete the work in:
Time=1Combined work rate=10019 days

Step 7: Set up the equation based on the problem statement
According to the problem, A, B, and C together take 40 days to complete the work. We can set up the equation:
10019=40

Step 8: Calculate the work done by C alone
Let x be the number of days C takes to complete the work alone. We know that:
10019 (time taken by A, B, and C)=40 (given time)
Now, we can find x using the relationship:
10019x=2540

Step 9: Solve for x
Cross-multiplying gives:
100x=192540
Calculating the right side:
100x=19000
Now, divide both sides by 100:
x=190

Step 10: Find the number of days C alone can complete the work
Since we need to find how many days C alone can complete the work:
x=190 days

Final Answer
C can complete the work alone in 190 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

    A5
    B6
    C10
    D8
  • Question 2 - Select One

    Gauthan and Karthik can do a piece of work in 10 days and 20 days respectively. With the help of Nilesh, they can complete the whole work in 5 days. In how many days can Nilesh alone complete the work ?

    A10
    B20
    C15
    D30
  • Question 3 - Select One

    Gauthan and Karthik can do a piece of work in 10 days and 20 days respectively. With the help of Nilesh, they can complete the whole work in 5 days. In how many days can Nilesh alone complete the work ?

    A10
    B20
    C15
    D30