A can build a wall in 25 days and B can demolish the same wall in 80 days and C can build the same wall in 60 days. If they work on consecutive days one after another starting from A on the first day. Then, in how many days will the work be completed?
67 days
671724 days
661724 days
681724 days
The correct Answer is:C
To solve the problem, we first need to determine the work done by A, B, and C in one day.
1. Calculate the work done by A in one day:
- A can build the wall in 25 days.
- Therefore, the work done by A in one day = 1/25 of the wall.
2. Calculate the work done by B in one day:
- B can demolish the wall in 80 days.
- Therefore, the work done by B in one day = -1/80 of the wall (negative because B is demolishing).
3. Calculate the work done by C in one day:
- C can build the wall in 60 days.
- Therefore, the work done by C in one day = 1/60 of the wall.
4. Determine the total work done in a 3-day cycle (A, B, C):
- Day 1 (A): Work done = 1/25
- Day 2 (B): Work done = -1/80
- Day 3 (C): Work done = 1/60
- Total work done in 3 days = (1/25) + (-1/80) + (1/60)
5. Find a common denominator to add the fractions:
- The least common multiple (LCM) of 25, 80, and 60 is 600.
- Convert each fraction:
- 1/25 = 24/600
- -1/80 = -7.5/600
- 1/60 = 10/600
- Total work done in 3 days = 24/600 - 7.5/600 + 10/600
- = (24 - 7.5 + 10) / 600
- = 26.5 / 600
- = 53/1200 of the wall in 3 days.
6. Calculate how many cycles are needed to complete the wall:
- To find out how many cycles (3 days) are needed to complete the wall, we need to find how many times 53/1200 fits into 1 (the whole wall).
- Number of cycles = 1 / (53/1200) = 1200/53 ≈ 22.64 cycles.
7. Calculate the total days to complete the wall:
- Each cycle takes 3 days.
- Total days = 22 cycles * 3 days/cycle = 66 days.
- Since we need to complete the wall, we will consider the remaining work after 22 cycles.
8. Calculate the remaining work after 66 days:
- Work done in 66 days = 22 cycles * (53/1200) = 1166/1200.
- Remaining work = 1 - 1166/1200 = 34/1200 = 17/600.
9. Determine how many more days are needed to complete the remaining work:
- After 66 days, it will be A's turn again (Day 67).
- A's work on Day 67 = 1/25.
- Convert 1/25 to the common denominator of 600 = 24/600.
- Remaining work = 17/600.
- Since A can complete 24/600 in one day, he will finish the remaining work on Day 67.
10. Final calculation of total days:
- Total days = 66 days (for 22 cycles) + 1 day (to complete the remaining work) = 67 days.
Thus, the total number of days required to complete the work is 67 days.
- A can build the wall in 25 days.
- Therefore, the work done by A in one day = 1/25 of the wall.
- B can demolish the wall in 80 days.
- Therefore, the work done by B in one day = -1/80 of the wall (negative because B is demolishing).
- C can build the wall in 60 days.
- Therefore, the work done by C in one day = 1/60 of the wall.
- Day 1 (A): Work done = 1/25
- Day 2 (B): Work done = -1/80
- Day 3 (C): Work done = 1/60
- Total work done in 3 days = (1/25) + (-1/80) + (1/60)
- The least common multiple (LCM) of 25, 80, and 60 is 600.
- Convert each fraction:
- 1/25 = 24/600
- -1/80 = -7.5/600
- 1/60 = 10/600
- Total work done in 3 days = 24/600 - 7.5/600 + 10/600
- = (24 - 7.5 + 10) / 600
- = 26.5 / 600
- = 53/1200 of the wall in 3 days.
- To find out how many cycles (3 days) are needed to complete the wall, we need to find how many times 53/1200 fits into 1 (the whole wall).
- Number of cycles = 1 / (53/1200) = 1200/53 ≈ 22.64 cycles.
- Each cycle takes 3 days.
- Total days = 22 cycles * 3 days/cycle = 66 days.
- Since we need to complete the wall, we will consider the remaining work after 22 cycles.
- Work done in 66 days = 22 cycles * (53/1200) = 1166/1200.
- Remaining work = 1 - 1166/1200 = 34/1200 = 17/600.
- After 66 days, it will be A's turn again (Day 67).
- A's work on Day 67 = 1/25.
- Convert 1/25 to the common denominator of 600 = 24/600.
- Remaining work = 17/600.
- Since A can complete 24/600 in one day, he will finish the remaining work on Day 67.
- Total days = 66 days (for 22 cycles) + 1 day (to complete the remaining work) = 67 days.
Topper's Solved these Questions
- IMO QUESTION PAPER 2018 SET BBOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2018 SET BEXERCISE - ACHIEVERS SECTION
5 Videos
- IMO QUESTION PAPER 2018 SET BBOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2018 SET BEXERCISE - ACHIEVERS SECTION
5 Videos
- IMO QUESTION PAPER 2018 SET ABOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2018 SET AEXERCISE - Achievers section
5 Videos
- IMO QUESTION PAPER 2019 SET ABOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2019 SET AEXERCISE - Achievers section
5 Videos
Similar Questions
Sanjeev can build a wall in 20 days and Parveen can demolish the same wall in 30 days. If they work on alternate days with Sanjeev starting the job on the 1st day, then in how many days will the wall be built for the first time ?
View SolutionA can build a wall in 15 days and B can build it in 10 days, while C can completely demolish the wall in 12 days. If they start working at the same time, in how many days will the work be completed.
View Solution
Knowledge Check
A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
A12B10C15D24A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?
A120 daysB118 daysC115 daysD110 daysIf P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?A73daysB83daysC103daysD113days
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionFour persons can build a wall in 12 days . How many persons will be required to build the same will in 8 days.
View SolutionRohan and Mohit together can build a wall in 8 days. Mohit and Vikas can build the same wall in 10 days and Vikas and Rohan can build the same wall in 12 days. In how many days can all the three complete the same wall while working together?
View SolutionRaja and Kundan together can build a wall in 20 days, Kundan and Mahesh build the same wall in 30 days and Mahesh and Raja can build the same wall in 24 days. In how many days can all the three complete the same wall while working together?
View SolutionA can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
View Solution