A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
100
110
55
50
The correct Answer is:B
Step by step video, text & image solution for A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was: by Maths experts to help you in doubts & scoring excellent marks in Class 7 exams.
Updated on:21/07/2023Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 13(b)
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- SIMPLE INTEREST BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMPLE INTEREST EXERCISE - Self Assessment Sheet
10 Videos
- TRIANGLESBOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLESEXERCISE - Self Assessment Sheet - 18
10 Videos
Similar Questions
Knowledge Check
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
A100B110C55D50A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
Aa. 10%Bb. 1427%Cc. 20%Dd. can't be determinedA Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?
A10%B1427%C20%Dcan’t be determined
A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?
View SolutionHow many workers are required for completing the construction work in the 10 days ?
(i) 20% of the work can be completed by 8 workers in 8 days.
(ii) 20 workers can complete the work in 16 days.
(iii) One - eighth of the work can ve completed by 8 workers in 5 days.
View Solution56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.
View Solution