A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less. What was the actual strength of workers?
30 workers
40 workers
42 workers
36 workers
The correct Answer is:D
To solve the problem step by step, we can follow these instructions:
Step 1: Define the variables
Let the total number of workers be x.
Step 2: Calculate the total work done
If x workers can complete the job in 120 days, the total work can be expressed as:
Total Work=Number of Workers×Number of Days=120x
Step 3: Work done with additional workers
If there are 4 more workers, then the total number of workers becomes x+4. The work can be completed in 12 days less, which means it will take 120−12=108 days. Therefore, the total work can also be expressed as:
Total Work=(x+4)×108
Step 4: Set the equations equal
Since both expressions represent the same total work, we can set them equal to each other:
120x=(x+4)×108
Step 5: Expand and simplify the equation
Expanding the right side gives:
120x=108x+432
Step 6: Rearrange the equation
Now, we can rearrange the equation to isolate x:
120x−108x=432
12x=432
Step 7: Solve for x
Dividing both sides by 12 gives:
x=43212=36
Conclusion
The actual strength of the workers is 36.
Let the total number of workers be x.
If x workers can complete the job in 120 days, the total work can be expressed as:
Total Work=Number of Workers×Number of Days=120x
If there are 4 more workers, then the total number of workers becomes x+4. The work can be completed in 12 days less, which means it will take 120−12=108 days. Therefore, the total work can also be expressed as:
Total Work=(x+4)×108
Since both expressions represent the same total work, we can set them equal to each other:
120x=(x+4)×108
Expanding the right side gives:
120x=108x+432
Now, we can rearrange the equation to isolate x:
120x−108x=432
12x=432
Dividing both sides by 12 gives:
x=43212=36
The actual strength of the workers is 36.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View Solution
Knowledge Check
a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
A17B24C30D22A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
A17B24C30D22A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
A50B40C56D58
A certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?
View SolutionA certain number of men can complete a job in 30 days. If there were 5 men more, it could be completed in 10 days less. How many men were in the beginning?
View Solution