A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
5
4
3
6
The correct Answer is:A
To solve the problem, we will follow these steps:
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 12 days, so in one day, A does:
Work done by A in one day=112 of the work
- B can complete the work in 18 days, so in one day, B does:
Work done by B in one day=118 of the work
- C can complete the work in 9 days, so in one day, C does:
Work done by C in one day=19 of the work
Step 2: Calculate the total work in a common unit.
To make calculations easier, we can assume the total work is 36 units (the least common multiple of 12, 18, and 9).
- Work done by A in one day:
A's work in one day=3612=3 units
- Work done by B in one day:
B's work in one day=3618=2 units
- Work done by C in one day:
C's work in one day=369=4 units
Step 3: Calculate the work done by A in 4 days.
- Work done by A in 4 days:
Work done by A=4×3=12 units
Step 4: Calculate the work done by B in 2 days.
- Work done by B in 2 days:
Work done by B=2×2=4 units
Step 5: Calculate the total work done by A and B.
- Total work done by A and B:
Total work done=12+4=16 units
Step 6: Calculate the remaining work.
- Remaining work:
Remaining work=36−16=20 units
Step 7: Calculate the number of days C will take to complete the remaining work.
- Since C can do 4 units of work in one day, the number of days C will take to complete the remaining work is:
Days taken by C=204=5 days
Final Answer:
C will take 5 days to complete the remaining work.
---
- A can complete the work in 12 days, so in one day, A does:
Work done by A in one day=112 of the work
- B can complete the work in 18 days, so in one day, B does:
Work done by B in one day=118 of the work
Work done by C in one day=19 of the work
To make calculations easier, we can assume the total work is 36 units (the least common multiple of 12, 18, and 9).
- Work done by A in one day:
A's work in one day=3612=3 units
- Work done by B in one day:
B's work in one day=3618=2 units
C's work in one day=369=4 units
- Work done by A in 4 days:
Work done by A=4×3=12 units
- Work done by B in 2 days:
Work done by B=2×2=4 units
- Total work done by A and B:
Total work done=12+4=16 units
- Remaining work:
Remaining work=36−16=20 units
- Since C can do 4 units of work in one day, the number of days C will take to complete the remaining work is:
Days taken by C=204=5 days
C will take 5 days to complete the remaining work.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)
20 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
View Solution
Knowledge Check
A and B can do a piece of work in 24 and 30 days respectively.
Both started the work and worked for 6 days. Then B leaves
the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
alone can do the workA80B100C120D130A, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?A659daysB629daysC6 daysD549daysA, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
A2B52C114D95
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View SolutionA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
View SolutionA and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?
View Solution