A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

A

5

B

4

C

3

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we will follow these steps:

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 12 days, so in one day, A does:
Work done by A in one day=112 of the work

- B can complete the work in 18 days, so in one day, B does:
Work done by B in one day=118 of the work

- C can complete the work in 9 days, so in one day, C does:
Work done by C in one day=19 of the work

Step 2: Calculate the total work in a common unit.
To make calculations easier, we can assume the total work is 36 units (the least common multiple of 12, 18, and 9).
- Work done by A in one day:
A's work in one day=3612=3 units

- Work done by B in one day:
B's work in one day=3618=2 units

- Work done by C in one day:
C's work in one day=369=4 units

Step 3: Calculate the work done by A in 4 days.
- Work done by A in 4 days:
Work done by A=4×3=12 units

Step 4: Calculate the work done by B in 2 days.
- Work done by B in 2 days:
Work done by B=2×2=4 units

Step 5: Calculate the total work done by A and B.
- Total work done by A and B:
Total work done=12+4=16 units

Step 6: Calculate the remaining work.
- Remaining work:
Remaining work=3616=20 units

Step 7: Calculate the number of days C will take to complete the remaining work.
- Since C can do 4 units of work in one day, the number of days C will take to complete the remaining work is:
Days taken by C=204=5 days

Final Answer:
C will take 5 days to complete the remaining work.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 24 and 30 days respectively.
    Both started the work and worked for 6 days. Then B leaves
    the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
    alone can do the work

    A80
    B100
    C120
    D130
  • A, b and C can alone complete a work in 10, 12 and 15 days
    respectively. A and C started the work and after working for
    4 days, A left and B joined. In how many days the total work
    was completed ?

    A659days
    B629days
    C6 days
    D549days
  • A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95