Doubtnut Promotions Sticky

Certain men can do a piece of work in 22 days. If the number of men decreses by 55, then they will take 11 days more to comlete the same work. Find the number of men present intially.

A

165

B

155

C

185

D

175

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we will follow these steps:

Step 1: Define Variables
Let the number of men initially be X.

Step 2: Calculate Work Done by Initial Men
If X men can complete the work in 22 days, the total work can be expressed in terms of man-days:
Total Work=X×22

Step 3: Calculate Work Done by Reduced Number of Men
When the number of men decreases by 55, the number of men becomes X55. According to the problem, these men take 11 days more, which means they complete the work in:
22+11=33 days
The total work done by these men can also be expressed as:
Total Work=(X55)×33

Step 4: Set Up the Equation
Since both expressions represent the same total work, we can set them equal to each other:
X×22=(X55)×33

Step 5: Expand and Rearrange the Equation
Expanding the right side:
22X=33X55×33
22X=33X1815
Now, rearranging the equation to isolate X:
22X33X=1815
11X=1815
Dividing both sides by -11:
X=181511
X=165

Step 6: Conclusion
Thus, the number of men present initially is 165.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :

    A15
    B30
    C20
    D35
  • Question 2 - Select One

    If x men can do a piece of work In x days, then the number of days in which y men can do the same work is

    Axy days
    By2x days
    Cx2y days
    Dx2y days
  • Question 3 - Select One

    If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :

    A38
    B28
    C19
    D17