Doubtnut Promotions Sticky

Fifteen men take 10 days to complete a job working 12hours a day. How many hours in a day should 10 men work to complete the same job in 20 days?

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we can follow these calculations:

Step 1: Calculate the total work done in man-hours
We know that 15 men take 10 days to complete the job, working 12 hours a day.

Total work (in man-hours) = Number of men × Number of days × Number of hours per day

Total work=15 men×10 days×12 hours/day=1800 man-hours

Step 2: Set up the equation for the second scenario
Now, we need to find out how many hours (H) per day 10 men should work to complete the same job in 20 days.

Using the same formula for work:

Total work=10 men×20 days×H hours/day

Step 3: Equate the two expressions for work
Since the total work remains the same, we can set the two equations equal to each other:

1800 man-hours=10 men×20 days×H hours/day

Step 4: Solve for H
Now we can solve for H:

1800=200H

Dividing both sides by 200:

H=1800200=9 hours

Conclusion
Thus, 10 men should work 9 hours a day to complete the job in 20 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men take 20 days to com plete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days

    A5 hours
    B10 hours
    C15 hours
    D18 hours
  • Question 2 - Select One

    Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.

    A30 days
    B45 days
    C60 days
    D15 days
  • Question 3 - Select One

    If 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.

    A6 hours
    B(6)1/2 hours
    C7 hours
    D9 hours