Doubtnut Promotions Sticky

Fifteen men take 10 days to complete a job working 12hours a day. How many hours in a day should 10 men work to complete the same job in 20 days?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Since 15 men take 10 days working 12 hourse per dat, the total work done measured in terms of man-hours is 15×10×12
When 10 men are required to complete th same job in 20 days working h hourse a day work done =10×20×h.But 10×20×h=15×10×12. Hence, the number of hours for which they should work per day is 15×10×1210×20=9
10 men can complete the work in 20 days working for 9 hours per day.
Hence in general we can say that :
If M1 men can do W1 work in D1 day working H1 hourse per day and M2 men can do W2 work in D2 days working H2 hourse H2 hours per day (where all men work at the same rate), then M1D1H1W1=M2D2H2W2

|
Updated on:21/07/2023

Related Playlists


Similar Questions