If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days
6
5
4
2
The correct Answer is:C
To solve the problem, we need to determine how many men should join 3 women to complete the work in 16 days, given that 4 men or 6 women can complete the work in 24 days.
Step 1: Determine the total work in terms of man-days.
Since 4 men can complete the work in 24 days, the total work can be calculated as:
Total Work=Number of Men×Days=4 men×24 days=96 man-days
Step 2: Determine the work done by 3 women in 16 days.
First, we need to find out how much work one woman can do in one day. Since 6 women can complete the work in 24 days, we can calculate the work done by one woman in one day:
Work done by 1 woman in 1 day=96 man-days6 women×24 days=96144=23 man-days
Now, the work done by 3 women in one day is:
Work done by 3 women in 1 day=3×23=2 man-days
In 16 days, the total work done by 3 women is:
Total work done by 3 women in 16 days=2 man-days/day×16 days=32 man-days
Step 3: Calculate the remaining work to be done.
The total work is 96 man-days, and the work done by 3 women in 16 days is 32 man-days. Therefore, the remaining work is:
Remaining Work=96 man-days−32 man-days=64 man-days
Step 4: Determine how many men are needed to complete the remaining work in 16 days.
Let x be the number of men required. The total work done by x men in 16 days is:
Work done by x men in 16 days=x×16 man-days
We set this equal to the remaining work:
x×16=64
Solving for x:
x=6416=4
Conclusion:
Therefore, 4 men should join the 3 women to complete the work in 16 days.
---
Since 4 men can complete the work in 24 days, the total work can be calculated as:
Total Work=Number of Men×Days=4 men×24 days=96 man-days
First, we need to find out how much work one woman can do in one day. Since 6 women can complete the work in 24 days, we can calculate the work done by one woman in one day:
Work done by 1 woman in 1 day=96 man-days6 women×24 days=96144=23 man-days
Work done by 3 women in 1 day=3×23=2 man-days
Total work done by 3 women in 16 days=2 man-days/day×16 days=32 man-days
The total work is 96 man-days, and the work done by 3 women in 16 days is 32 man-days. Therefore, the remaining work is:
Remaining Work=96 man-days−32 man-days=64 man-days
Let x be the number of men required. The total work done by x men in 16 days is:
Work done by x men in 16 days=x×16 man-days
We set this equal to the remaining work:
x×16=64
Solving for x:
x=6416=4
Therefore, 4 men should join the 3 women to complete the work in 16 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)
20 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
Knowledge Check
If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?
A38B32C40D35If 12 men or 18 women can do a piece of work in 14 days, then how long will 8 men and 16 women take to finish the work ?
A9 daysB10 daysC12 daysD14 daysIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
A4 daysB5 daysC3 daysD2 days
If 5 men or 9 women can do a piece of work in 19 days, then in how many days will 3 men and 6 women do the same work? 12 b. 15 c. 18 d. 21
View Solution4 men & 18 women can do a piece of work in 2.5 days, then in how many days 12 woment can complete the same piece of work ?
A. Ratio of efficiency of men to woment is 3:2.
B. 6 men & 6 women can complete the dame work in 4 days.
View SolutionFour men and 6 women can complete a certain piece of work in 5 days whereas three men and 4 women can complete it in 7 days. How many men should assist 25 women to complete times the same work in 5 days?
View SolutionIf 4 men or 6 women can do a piece of work in 12 days workIng 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day?
View SolutionIf 16 men or 20 women can do a piece of work in 25 days, in what time will 28 men and 15 women do it ?
View Solution