If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the
same work in 6 days, how long will 6 men and 24 boys take to complete the same work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Given that,9m+12b can do the work in 4days and 4m+16b can do the same work in 6 days.
4(9m+12b)=6(4m+16b)m=4b
Now, 9m+12b=9(4b)+12b=48b and
6m+24b=6(4b)+24b=48b
6 men and 24 boys also take 4 days to complete the work.
ALTERMATE METHOD
(4m+16b) can do the work in 6 days.
32(4m+16b) can do the work in (6×23) days.
(6m+24b) can do the work in 4 days.

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

    A2 days
    B4 days
    C6 days
    D16 days
  • 2 men and 7 boys can do a piece of work in 4 days . 4 men and 4 boys can do the same work in 3 days . Then the number of days a boys a boy take to complete the same job is .

    A50 days
    B60 days
    C30 days
    D55 days
  • If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be
    A)6 days
    B)4 days
    C)8 days
    D)7 days

    A6 days
    B4 days
    C8 days
    D7 days