Doubtnut Promotions Sticky

12 men and 16 boys can do a piece of work in 5 days. 13 men and 24 boys can do the same work in 4 days. How long will 7 men and 10 boys take to do the same work?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is: 8 1 3 days.


To solve the problem, we need to determine how long it will take for 7 men and 10 boys to complete the same piece of work given the efficiencies of men and boys based on the information provided.

1. Define Variables:
Let the efficiency of one man be m and the efficiency of one boy be b.

2. Set Up Equations from Given Information:
From the first scenario:
- 12 men and 16 boys can complete the work in 5 days.
- The total work done can be expressed as:
Total Work=Efficiency×Time=(12m+16b)×5
Thus, we have:
60m+80b=W(1)

From the second scenario:
- 13 men and 24 boys can complete the work in 4 days.
- The total work done can be expressed as:
Total Work=(13m+24b)×4
Thus, we have:
52m+96b=W(2)

3. Equate the Two Expressions for Total Work:
Since both expressions equal the total work W, we can set them equal to each other:
60m+80b=52m+96b

4. Simplify the Equation:
Rearranging gives:
60m52m=96b80b
8m=16b
Dividing both sides by 8 gives:
m=2b(3)

5. Substitute m in One of the Work Equations:
We can substitute m from equation (3) into equation (1):
60(2b)+80b=W
120b+80b=W
200b=W
Thus, the total work W is 200b.

6. Find the Efficiency of 7 Men and 10 Boys:
Now, we calculate the efficiency of 7 men and 10 boys:
Efficiency=7m+10b
Substituting m=2b:
=7(2b)+10b=14b+10b=24b

7. Calculate the Time Taken by 7 Men and 10 Boys:
The time taken to complete the work is given by:
Time=Total WorkEfficiency=200b24b
The b cancels out:
=20024=253 days
Converting this to a mixed number:
=813 days

Final Answer:
Therefore, the time required for 7 men and 10 boys to complete the work is 813 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

    A2 days
    B4 days
    C6 days
    D16 days
  • Question 2 - Select One

    2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?

    A1212 days
    B1112 days
    C1512 days
    D1312 days
  • Question 3 - Select One

    If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be
    A)6 days
    B)4 days
    C)8 days
    D)7 days

    A6 days
    B4 days
    C8 days
    D7 days