If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:4 days


To solve the problem, we need to find out how long it will take for 15 men and 20 boys to complete the same work given the work rates of men and boys from the previous information.

1. Determine the Work Done by 6 Men and 8 Boys in 10 Days:
- Let the work done by 1 man in 1 day be M units.
- Let the work done by 1 boy in 1 day be B units.
- Therefore, the total work done by 6 men and 8 boys in 10 days can be expressed as:
(6M+8B)×10=60M+80B

2. Determine the Work Done by 26 Men and 48 Boys in 2 Days:
- Similarly, the total work done by 26 men and 48 boys in 2 days is:
(26M+48B)×2=52M+96B

3. Set the Two Work Equations Equal:
- Since both expressions represent the same total work, we can set them equal to each other:
60M+80B=52M+96B

4. Rearrange the Equation:
- Rearranging gives:
60M52M=96B80B
8M=16B
- Simplifying this gives:
M=2B

5. Calculate Total Work in Terms of Units:
- Now, substitute M in terms of B back into the first equation to find the total work:
60M+80B=60(2B)+80B=120B+80B=200B
- Thus, the total work is 200B units.

6. Determine the Work Done by 15 Men and 20 Boys:
- Now we calculate the work done by 15 men and 20 boys:
Work done by 15 men=15M=15(2B)=30B
Work done by 20 boys=20B
- Therefore, the total work done by 15 men and 20 boys in one day is:
30B+20B=50B

7. Calculate the Time Taken to Complete the Work:
- To find the time taken to complete 200B units of work at a rate of 50B units per day:
Time=Total WorkWork per Day=200B50B=4 days

Final Answer:
The time taken by 15 men and 20 boys to complete the work is 4 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :

    A5 days
    B4 days
    C6 days
    D7 days
  • If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be
    A)6 days
    B)4 days
    C)8 days
    D)7 days

    A6 days
    B4 days
    C8 days
    D7 days
  • If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

    A2 days
    B4 days
    C6 days
    D16 days