If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :
The correct Answer is:4 days
To solve the problem, we need to find out how long it will take for 15 men and 20 boys to complete the same work given the work rates of men and boys from the previous information.
1. Determine the Work Done by 6 Men and 8 Boys in 10 Days:
- Let the work done by 1 man in 1 day be M units.
- Let the work done by 1 boy in 1 day be B units.
- Therefore, the total work done by 6 men and 8 boys in 10 days can be expressed as:
(6M+8B)×10=60M+80B
2. Determine the Work Done by 26 Men and 48 Boys in 2 Days:
- Similarly, the total work done by 26 men and 48 boys in 2 days is:
(26M+48B)×2=52M+96B
3. Set the Two Work Equations Equal:
- Since both expressions represent the same total work, we can set them equal to each other:
60M+80B=52M+96B
4. Rearrange the Equation:
- Rearranging gives:
60M−52M=96B−80B
8M=16B
- Simplifying this gives:
M=2B
5. Calculate Total Work in Terms of Units:
- Now, substitute M in terms of B back into the first equation to find the total work:
60M+80B=60(2B)+80B=120B+80B=200B
- Thus, the total work is 200B units.
6. Determine the Work Done by 15 Men and 20 Boys:
- Now we calculate the work done by 15 men and 20 boys:
Work done by 15 men=15M=15(2B)=30B
Work done by 20 boys=20B
- Therefore, the total work done by 15 men and 20 boys in one day is:
30B+20B=50B
7. Calculate the Time Taken to Complete the Work:
- To find the time taken to complete 200B units of work at a rate of 50B units per day:
Time=Total WorkWork per Day=200B50B=4 days
Final Answer:
The time taken by 15 men and 20 boys to complete the work is 4 days.
---
- Let the work done by 1 man in 1 day be M units.
- Let the work done by 1 boy in 1 day be B units.
- Therefore, the total work done by 6 men and 8 boys in 10 days can be expressed as:
(6M+8B)×10=60M+80B
- Similarly, the total work done by 26 men and 48 boys in 2 days is:
(26M+48B)×2=52M+96B
- Since both expressions represent the same total work, we can set them equal to each other:
60M+80B=52M+96B
- Rearranging gives:
60M−52M=96B−80B
8M=16B
- Simplifying this gives:
M=2B
- Now, substitute M in terms of B back into the first equation to find the total work:
60M+80B=60(2B)+80B=120B+80B=200B
- Thus, the total work is 200B units.
- Now we calculate the work done by 15 men and 20 boys:
Work done by 15 men=15M=15(2B)=30B
Work done by 20 boys=20B
- Therefore, the total work done by 15 men and 20 boys in one day is:
30B+20B=50B
- To find the time taken to complete 200B units of work at a rate of 50B units per day:
Time=Total WorkWork per Day=200B50B=4 days
The time taken by 15 men and 20 boys to complete the work is 4 days.
Topper's Solved these Questions
Similar Questions
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be 4 days b. 5 days c. 6 days d. 7 days
View SolutionIf 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the
same work in 6 days, how long will 6 men and 24 boys take to complete the same work?
View Solution
Knowledge Check
If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :
A5 daysB4 daysC6 daysD7 daysIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be
A)6 days
B)4 days
C)8 days
D)7 daysA6 daysB4 daysC8 daysD7 daysIf 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in
A2 daysB4 daysC6 daysD16 days
If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same work in 6 days, how long will 6 men and 24 boys take to complete the same work?
View Solution2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the work?
View Solution12 men and 16 boys can do a piece of work in 5 days. 13 men and 24 boys can do the same work in 4 days. How long will 7 men and 10 boys take to do the same work?
View Solution2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?
View SolutionIf 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be
View Solution