Doubtnut Promotions Sticky

P and Q can do a piece of work in 12 days 16 days, resepetively. With the help of R, they completed the work in 5 days and earn Rs. 912. What is the share of R?

A

Rs. 249

B

Rs. 247

C

Rs. 243

D

Rs. 245

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine the share of R in the total earnings of Rs. 912 after P, Q, and R completed the work together in 5 days. Here’s a step-by-step solution:

Step 1: Determine the work rates of P and Q
- P can complete the work in 12 days, so the work done by P in one day is:
Work rate of P=112
- Q can complete the work in 16 days, so the work done by Q in one day is:
Work rate of Q=116

Step 2: Calculate the combined work rate of P and Q
- The combined work rate of P and Q in one day is:
Combined work rate of P and Q=112+116
- To add these fractions, we need a common denominator. The least common multiple of 12 and 16 is 48.
112=448,116=348
- Therefore,
Combined work rate of P and Q=448+348=748

Step 3: Calculate the total work done by P and Q in 5 days
- In 5 days, the amount of work done by P and Q together is:
Work done by P and Q in 5 days=5×748=3548

Step 4: Determine the work done by R
- Since the total work is considered as 1 (or 100%), the work done by R in 5 days is:
Work done by R=13548=48483548=1348

Step 5: Calculate the earnings of P, Q, and R
- The total earnings for the work completed is Rs. 912.
- The share of earnings is proportional to the amount of work done by each person.
- The total work done by P and Q together is 3548 and by R is 1348.

Step 6: Calculate the earnings of P and Q
- The earnings of P and Q together can be calculated as:
Earnings of P and Q=3548×912=35×91248
- Simplifying this:
35×91248=665

Step 7: Calculate R's earnings
- R's share of the total earnings is:
Earnings of R=912665=247

Final Answer
Thus, R's share of the earnings is Rs. 247.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 6 days and 8 days, respectively. With the help of C, they completed the work in 3 days and earned 1,848. What was the share of C ?

    A231
    B924
    C462
    D693
  • Question 2 - Select One

    A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

    A9 days
    B18 days
    C6 days
    D4 days
  • Question 3 - Select One

    Gauthan and Karthik can do a piece of work in 10 days and 20 days respectively. With the help of Nilesh, they can complete the whole work in 5 days. In how many days can Nilesh alone complete the work ?

    A10
    B20
    C15
    D30